RERA project · Residential/Group Housing
PAVANI MIRABILIA PHASE I
by Sai Sravanthi Infra Projects Pvt Ltd · 1,006 homes · 13.41 acres · 6 towers · Bengaluru East
Upcoming Under construction, due May 2028. 87% built with 72% of the time used. 42% of homes booked.
At a glance
Due 25 May 2028. 72% of the time from RERA approval to the deadline has passed.
465 of 1,108 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 80 per acre. 79% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 3 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started19 May 2022
- Approved by RERA12 Sep 2022
- Today24 Oct 2026
72% of the time to the deadline has passed.
- Deadline25 May 2028
The date it must be complete by.
- If it slips like a typical project24 Feb 2029
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 87 × 2BHK, 128 × 2 BHK, 200 × 3 BHK, 30 × 4 BHK, 198 × 1 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower A: 158 homes, 2 basements · Tower B: 158 homes, 2 basements · Tower C: 238 homes, 2 basements · Tower D: 238 homes, 2 basements · Tower H: 80 homes, 2 basements · Tower J: 236 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 13.41 acres
- Ground covered by buildings
- 21% of the land
- Floor-area ratio
- 4.00
- Parking
- 2.29 per home
- Built-up area, all floors
- 15,86,889 sq ft
54,278 m²
11,485 m²
Floors built per unit of land: 4.00 m² of floors for each m² of land.
984 covered, 167 open
1,47,427 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 4 RERA projects of Sai Sravanthi Infra Projects Pvt Ltd on the map
The company
- Registered as
- Sai Sravanthi Infra Projects Pvt Ltd
- Type
- Company
- Company number
- U45203TG2008PTC060151
- PAN
- AAPCS0464C
- GSTIN
- 29AAPCS0464C1Z9
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- PAVANI MIRABILIA PHASE III PRM/KA/RERA/1251/446/PR/240626/008750 · approved 24 Jun 2026
- PAVANI MIRABILIA PHASE-II PRM/KA/RERA/1251/446/PR/200224/006641 · approved 20 Feb 2024
- Pavani Divine PRM/KA/RERA/1251/446/PR/171031/001412 · approved 31 Oct 2017
The land is owned together with others (a joint development), including DSR INFRASTRUCTURE PVT LTD.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/120922/005235 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/EM/EA-01/TA-4/E/07/2022-23 · 19 May 2022
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceLocal Authority
Complaints to RERA about this project
- Complaint under Sec 31 of the Real Estate Act 2016, misrepresentation of litigation status (Section 12), failure to update project disclosures (Section 11), & contract delivery timeline breach(Sec 18) 16 Apr 2026 · Disposed Authority Fullbench
- Delay in possession of Apt J-801 & J-802, 8th Floor, Tower J, Pavani Mirabilia Phase I — Possession promised by 31-12-2025, grace period expired 30-06-2026, possession not offered till date 10 Aug 2026 · Disposed Authority Fullbench
- Complaint regarding delay in possession and non-responsive communication – Pavani Mirabilia Phase 1, Flat D-208 16 Sep 2026 · Under Enquiry Authority Fullbench
Documents
189 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q1 2026-27 | ₹1.2 cr | ₹11.7 cr |
| Q2 2026-27 | ₹2.8 cr | ₹2.8 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station2.41 kmReliable
- Nearest railway station2.3 kmReliable
- Bus stops within 500 m2Caveat
Parks, shops, daily needs
- Supermarkets within 1 km4Caveat
- Parks within 1 km11Caveat
- Nearest lake / water body (≥2 ha)0.88 kmCaveat
Hospitals
- Nearest hospital0.95 kmCaveat
Schools
- Schools in pincode 560067 (UDISE+ census)57Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km8Caveat
- Median pupil-teacher ratio, schools within 1 km20.1 :1Caveat
- Schools with library + playground + ICT lab (1 km)6Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionKadugodi PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well60.8 m below groundCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km1Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)7.97 kmReliable
- Nearest sewage treatment plant2.41 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)5.38 kmCaveat
- Nearest commercial-airport runway19.42 kmReliable
- Distance to runway approach-path proxy17.87 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (13.01715, 77.76233), 2026-10-24. Each figure's source and caveat are in the full report.