RERA project · Residential/Group Housing
Pashmina Waterfront -Phase-I
by Lily Realty Pvt Ltd · 672 homes · 7.75 acres · 5 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 11 Aug 2020, 589 days after the date it first promised.
At a glance
The builder filed for completion on 11 Aug 2020, 589 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 88% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started19 Oct 2012
- Approved by RERA14 Oct 2017
- Completion filed11 Aug 2020
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
Block A: 149 homes, 3 basements · Block B: 149 homes, 3 basements · Block C: 76 homes, 3 basements · Block D: 149 homes, 3 basements · Block E: 149 homes, 3 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 7.75 acres
- Ground covered by buildings
- 12% of the land
31,363 m²
3,902 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Lily Realty Pvt Ltd
- Type
- Company
- Company number
- U45400MH2007PTC169296
- PAN
- AABCL2976N
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171014/000345 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Non-completion of project by promised date 16 Jun 2019 · Disposed Ao
- The Apt scheduled handover date was 30.06.15 including 6 months grace period. The apt is still not complete in all respect. 12 Jul 2019 · Disposed Ao
- Delay in handover, incorrect charges and for the harassment and wasted time, and not being able to buy and use any alternative either 29 Jul 2019 · Disposed Ao
- Deviation in clubhouse plan and poor workmanship in flat 31 Aug 2019 · Disposed Ao
- 5 Year Delay, Breach of Agreement, Full Refund and 10% interest compensation 5 Nov 2019 · Disposed Ao
- Claiming damages and Compensation for the delay cost by the Promoter 8 Nov 2019 · Disposed Ao
- Property not delivered. Need my money back with interest 12 Nov 2019 · Disposed Ao
- Delayed and pending for long time.request refund with interest and penalty relief 19 Nov 2019 · Disposed Ao
- Compensation for delay in completion and handover of FLAT T0207A at Pashmina Waterfront 12 Jul 2020 · Disposed Authority Bench6
- RERA Order with respect to complaint 1911050004558 Not Honored By Promoter after more than 70 days 22 Aug 2020 · Disposed Ao
- COMPLAINT UNDER SECTION 31 R/W SECTION 71 OF THE REAL ESTATE (REGULATION & DEVELOPMEMT) ACT, 2016 AND RULE 30 (1) OF THE KARNATAKA REAL ESTATE (REGULATION & DEVELOPMENT) RULES, 2017 26 Aug 2020 · Disposed Authority Bench6
- Delay in Delivery of Possession 25 Sep 2020 · Disposed Authority Bench6
- Delay in Delivery of Possession 25 Sep 2020 · Disposed Authority Bench6
- Developer hasn't delivered on what he has promised 14 Oct 2020 · Disposed Authority Bench6
- Flat & Project incomplete even after 6 years of delay 9 Nov 2020 · Disposed Ao
- Possession of flat not given 27 Dec 2020 · Disposed Authority Bench6
- Harassment by developer/builder for apartment not handed over as per allotment letter/construction Agreement and Delay Compensation 9 Mar 2021 · Disposed Authority Bench5
- Delay Compensation for Apartment T2A04A 15 Mar 2021 · Disposed Authority Bench4
- Amenities not completed as per Agreement even after 6 years 28 Apr 2021 · Disposed Ao
- Complaint Under Section 18 and 19 of the Real Estate (Regulation and Development) Act, 2017 30 Jun 2021 · Disposed Authority Fullbench
- Breach of Commitment/Contract 30 Jun 2021 · Posted For Orders Authority Fullbench
- Extraordinary dealy in apartment handover - full money paid almost 3 years ago 30 Jun 2021 · Posted For Orders Authority Fullbench
- Compensation for delay in apartment completion 4 Jul 2021 · Disposed Authority Bench6
- Apartment not handed over as per promised date 26 Jul 2021 · Disposed Authority Bench5
- Possession & Delay Compensation 26 Jul 2021 · Disposed Authority Fullbench
- Request for compensation for delay in delivery of apartment 26 Jul 2021 · Disposed Authority Bench4
- None Provision of Amenities excess PLC charges , Flat area shortage 5 Aug 2021 · Disposed Ao
- Project incomplete 6 Aug 2021 · Disposed Ao
- Complaint against Promoter for violation of provisions of the RERA and applicable agreements 18 Aug 2021 · Under Enquiry Authority Fullbench
- Incomplete apartment 8 Nov 2021 · Disposed Authority Fullbench
- Delay in Handover - penalty compensation not given 6 Dec 2021 · Posted For Orders Authority Fullbench
- Refund of the entire sale consideration along with refund of Pre-EMI interest and exit the project 1 Feb 2022 · Posted For Orders Authority Fullbench
- Refund of advance 30 Apr 2022 · Posted For Orders Authority Fullbench
- Reg T2-35-B _ Refund required due to false commitment 10 May 2022 · Disposed Authority Bench5
- Delay compensation and Refund of Pre EMI amount paid by the Petitioner 20 May 2022 · Disposed Authority Bench5
- Inordinate delay in completion of the Flat T0435A 30 May 2022 · Disposed Authority Bench5
- Delay in handing over the possession, pending work, Allotment of car parking space not in accordance with the Agreement to Sell and Construction Agreement, Interest on Installment Paid. 11 Aug 2022 · Disposed Authority Bench5
- Refund with interest 7 Oct 2022 · Disposed Authority Bench5
- REFUND OF THE BOOKING AMOUNT OF RS.10,60,000/- 12 Nov 2022 · Disposed Authority Bench5
- Failure to deliver apartment by agreement date. 26 Dec 2022 · Disposed Authority Bench5
- FAILED TO DELIVER THE FLAT BEARING NO.T0434D ON TIME WITH ALL AMENITIES. 31 Jan 2023 · Disposed Authority Bench5
- Absolute negligence and deficiency of service on the part of the RESPONDENT in completing the construction and delivering the possession of the flat to the complainants as agreed upon. 31 Jan 2023 · Disposed Authority Bench5
- Refund of Advance/Booking Amount Paid 22 Jun 2023 · Disposed Authority Bench5
- Refund with compensation 25 Aug 2023 · Disposed Authority Bench5
- Delivery date has been expired we need possession and interest on delay period till date . 9 Apr 2025 · Disposed Authority Bench5
- Violations of Section 11(4)(d),Sec14(3),Sec (17) 8 Apr 2026 · Under Enquiry Authority Bench5
Documents
73 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹55.6 cr
- Construction
- ₹910.1 cr
- Total project cost
- ₹965.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.