RERA project · Residential/Group Housing
Parkway Homes PH-II
by Parkway Homes LLP · 270 homes · 9.26 acres · 3 towers · Bengaluru South
Delivered late Completed: the builder filed for completion on 20 Jul 2019, 32 days after the date it first promised.
At a glance
The builder filed for completion on 20 Jul 2019, 32 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 82% of the land is left open.
Complaints to RERA about this project. 39 more about the builder's other projects.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised).
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started18 Oct 2013
- Approved by RERA31 Oct 2017
- Completion filed20 Jul 2019
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Edision: 90 homes, 2 basements · Franklin: 90 homes, 2 basements · Gelileo: 90 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 9.26 acres
- Ground covered by buildings
- 18% of the land
37,457 m²
6,907 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of PARKWAY HOMES LLP on the map
Complaints to RERA about its other projects
- PARKWAY HOMES 39 complaints
The company
- Registered as
- Parkway Homes LLP
- Type
- Partnership Firm
- PAN
- AAOFP4141K
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171031/001471 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Compensation for delay in completion of apartment 19 Apr 2019 · Disposed Ao
- Compensation for delay in completion of apartment 23 Apr 2019 · Disposed Ao
- Construction Delay and request for compensation in Parkway Homes project by Parkway Homes LLP 11 May 2019 · Disposed Authority Bench6
- Compensation for delay in completion of project 12 May 2019 · Disposed Ao
- Compensation for delay in completion of apartment 12 May 2019 · Disposed Ao
- No Possession Post Project End Date as per RERA 1 Aug 2019 · Disposed Ao
- Delay in handover, Possession & Delivery of Appartment & continues to be unfinished 17 Sep 2019 · Disposed Ao
- Delay in handover, Possession & Delivery of Appartment & continues to be unfinished 17 Sep 2019 · Disposed Ao
- Compensation for delay in completion of apartment 22 Sep 2020 · Disposed Ao
- Compensation for delay in completion of apartment 23 Sep 2020 · Disposed Ao
- Compensation for delay in completion of apartment 24 Sep 2020 · Disposed Ao
- Delay Compensation, Delay in Completion of Project 26 Sep 2020 · Disposed Authority Bench6
- Compensation for delay in completion of Apartment 21 Oct 2020 · Disposed Authority Bench6
- Compensation for delay in completion of apartment 5 Nov 2020 · Disposed Ao
- Compensation for delay in completion of apartment 6 Nov 2020 · Disposed Ao
Documents
45 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹56.6 cr
- Construction
- ₹237.8 cr
- Total project cost
- ₹294.4 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.