RERA project · Plotted Development
Oxigen Phase 1
by Excel Dwellings Oxigen Pvt Ltd · 47.57 acres · Anekal
Upcoming Under construction, due Aug 2028, after an extension. 40% built with 83% of the time used.
At a glance
Due 30 Aug 2028. 83% of the time from RERA approval to the deadline has passed.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started14 Feb 2014
- Approved by RERA31 Oct 2017
- First promised28 Feb 2022
The date the builder gave at registration.
- Today24 Oct 2026
83% of the time to the deadline has passed.
- Deadline (extended)30 Aug 2028
The date it must be complete by.
- If it slips like a typical project1 Jun 2029
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 47.57 acres
- Plot area (the sites)
- 55% of the land
1,92,527 m²
1,05,760 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Excel Dwellings Oxigen Pvt Ltd
- Type
- Company
- Company number
- U70200KA2014PTC074700
- PAN
- AADCE6857D
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171031/001644 · Transfered
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q3 2025-26 update
Complaints to RERA about this project
- Non Performance on the Delivery of the Amendments 24 Dec 2020 · Disposed Authority Fullbench
Documents
66 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹72.3 cr
- Construction
- ₹46.2 cr
- Total project cost
- ₹197.8 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹0.0 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.