Neighborhood IntelOpen on the map

RERA project · Plotted Development

ORCHARD AVENUE PHASE II

by G.M RAMESH · 7 plots · 0.37 acres · Anekal

Past due, no completion filed Past its deadline of 30 Jun 2025, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 30 Jun 2025, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
19 plots per acre

Similar projects within 3 km: 17 per acre. 55% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started20 Jun 2022
  2. Approved by RERA13 Jul 2022
  3. Deadline30 Jun 2025

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

ODD
—
6 plots · 86% of the project
EWS
—
1 plot · 14% of the project

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Plots per acre

This project19
Typical within 3 km (34)17
Typical in the city (593)16

Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project55%
Typical within 3 km (39)45%
Typical in the city (730)46%

The share of the land not built on, which includes roads.

Land
0.37 acres

1,517 m²

Plot area (the sites)
45% of the land

678 m²

Roads
603 m²
Parks and open spaces
235 m²
Civic amenity sites
678 m²

Sites kept for public uses such as a school or a health centre.

CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
G.M RAMESH
Type
Proprietorship Firm

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹2.2 crBuilding and development ₹95.0 lakhTotal ₹3.2 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.55 kmReliable
  • Nearest railway station4.42 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)0.85 kmCaveat

Hospitals

  • Nearest hospital3.04 kmCaveat

Schools

  • Schools in pincode 560099 (UDISE+ census)88Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)5.79 kmReliable
  • Nearest sewage treatment plant1.26 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)9.2 kmCaveat
  • Nearest commercial-airport runway35.46 kmReliable
  • Distance to runway approach-path proxy34.78 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.86895, 77.69459), 2026-10-24. Each figure's source and caveat are in the full report.