RERA project · Residential/Group Housing
Oceanus Classic
by Oceanus Dwellings Pvt Ltd · 201 homes · 2.64 acres · 4 towers · Bengaluru East
Upcoming Under construction, due Dec 2026, after an extension. 99% built with 98% of the time used. 45% of homes booked.
At a glance
Due 31 Dec 2026. 98% of the time from RERA approval to the deadline has passed.
91 of 201 homes, as the builder reported for Q3 2025-26.
Similar projects across the city: 76 per acre. 80% of the land is left open.
Complaints to RERA about this project. 10 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 5 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 1 past due with no completion filed, 2 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started28 Jun 2013
- Approved by RERA14 Dec 2017
- First promised28 Jun 2019
The date the builder gave at registration.
- Today24 Oct 2026
98% of the time to the deadline has passed.
- Deadline (extended)31 Dec 2026
The date it must be complete by.
- If it slips like a typical project2 Oct 2027
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q3 2025-26
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 83 × 2 BHK, 27 × 3 BHK.
Booked, by type
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower 1: 44 homes, 1 basement · Tower 2: 44 homes, 1 basement · Tower 3: 48 homes, 1 basement · Tower 4: 65 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 2.64 acres
- Ground covered by buildings
- 21% of the land
10,669 m²
2,191 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 5 RERA projects of Oceanus Dwellings Pvt Ltd on the map
Complaints to RERA about its other projects
- Oceanus Tranquil 5 complaints
- Oceanus Vista II T7 4 complaints
- CARMEL HEIGHTS 1 complaint
The company
- Registered as
- Oceanus Dwellings Pvt Ltd
- Type
- Company
- Company number
- U07010KA2003PTC031632
- PAN
- AAACO6011G
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171214/001027 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q3 2025-26 update
Complaints to RERA about this project
- Need to get Total Refund with Compensation due to delay in delivery of the project 23 Sep 2019 · Disposed Ao
- Delay in providing possession by the builder 19 Nov 2024 · Disposed Authority Bench4
Documents
71 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹27.7 cr
- Construction
- ₹41.5 cr
- Total project cost
- ₹69.2 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹1.4 cr | ₹1.0 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.