RERA project · Residential/Group Housing
Oak Leaf
by Suvastu Estates Pvt Ltd · 0.84 acres · Anekal
Past due, no completion filed Past its deadline of 31 Dec 2019, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2019, and no completion is filed.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Sep 2016
- Approved by RERA9 May 2018
- First promised31 Dec 2018
The date the builder gave at registration.
- Deadline (extended)31 Dec 2019
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.84 acres
- Ground covered by buildings
- 48% of the land
3,414 m²
1,653 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of Suvastu Estates Pvt Ltd on the map
The company
- Registered as
- Suvastu Estates Pvt Ltd
- Type
- Company
- PAN
- AASCS6537F
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/180509/001676 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Project Not Completed 4 Dec 2021 · Disposed Authority Bench5
- Delayed Project 4 Dec 2021 · Disposed Authority Bench5
- No permanent BESCOM connection along with amenities as promised 6 Dec 2021 · Disposed Authority Bench5
- Delayed Project 6 Dec 2021 · Disposed Authority Bench5
- Delayed project 7 Dec 2021 · Disposed Authority Bench5
- Delayed Project 8 Dec 2021 · Disposed Authority Bench5
- Project not completed, No BESCOM or Kaveri Water supply. 14 Dec 2021 · Disposed Authority Bench5
- DELAY IN EXECUTING THE SALE DEED OR TO REFUND THE SALE COSNIDERATION PAID UNDER THE AGREEMENT 14 May 2026 · Under Enquiry Authority Bench6
Documents
52 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹2.0 cr
- Construction
- ₹12.0 cr
- Total project cost
- ₹14.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station10.1 kmReliable
- Nearest railway station6.57 kmReliable
- Bus stops within 500 m6Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)0.63 kmCaveat
Hospitals
- Nearest hospital0.92 kmCaveat
Schools
- Schools in pincode 562125 (UDISE+ census)91Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km6Caveat
- Median pupil-teacher ratio, schools within 1 km23.5 :1Caveat
- Schools with library + playground + ICT lab (1 km)1Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionSarjapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)12.2 kmReliable
- Nearest sewage treatment plant7.12 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)11.33 kmCaveat
- Nearest commercial-airport runway34.27 kmReliable
- Distance to runway approach-path proxy32.81 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.88105, 77.76016), 2026-10-24. Each figure's source and caveat are in the full report.