Nitesh Hyde Park Phase II
by NITESH HOUSING DEVELOPERS PRIVATE LIMITED · 163 homes · 5.42 acres · 2 towers · Bengaluru South
Past due, no completion filed Past its deadline of 31 Dec 2018, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2018, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 74 per acre. 70% of the land is left open.
Complaints to RERA about this project. 56 more about the builder's other projects.
The RERA page doesn't say.
Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 3 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started17 May 2010
- Approved by RERA27 Jun 2018
- Deadline31 Dec 2018
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Block E: 98 homes, 1 basement · Block F: 65 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.42 acres
- Ground covered by buildings
- 30% of the land
21,954 m²
6,586 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 4 RERA projects of NITESH HOUSING DEVELOPERS PRIVATE LIMITED on the map
Complaints to RERA about its other projects
- Nitesh Melbourne Park 38 complaints
- Nitesh Columbus Square Phase II 14 complaints
- Nitesh Napa Valley 4 complaints
The company
- Registered as
- NITESH HOUSING DEVELOPERS PRIVATE LIMITED
- Type
- Company
- Company number
- U45201KA2007PTC044553
- PAN
- AACCN6510F
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/180627/001912 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Return of amount and compensation 26 Jun 2019 · Disposed Authority
- Refund - due to delay in completion of project 13 Jul 2019 · Disposed Ao
- Refund - due to delay in completion of project 21 Jul 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants seek interest for every month of delay and Pre-EMI reimbursement till the handing over of possession. 31 Jul 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 1 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 13 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 14 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay as well as Pre-EMI reimbursement till the handing over of p 14 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 20 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 22 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay as well as Pre-EMI reimbursement till hand over possession 23 Aug 2019 · Disposed Ao
- As the complainants do not intend to withdraw from the project at this stage, the complainants are seeking interest for every month of delay till the handing over of possession of the apartment. 3 Sep 2019 · Disposed Ao
- Inordinate delay in completion of project and handing over possession - Refund Request 3 Sep 2019 · Disposed Authority
- Refund of investment along with interest for failure to deliver apartment unit beyond due date 18 Sep 2019 · Disposed Ao
- compensation for delay in delivery of Apparent 19 Dec 2020 · Disposed Authority Bench6
- Complaint U/s. 63 of the Real Estate (Regulation & Development) Act, 2016 r/w. Rule 29 of the Karnataka Real Estate (Regulation and Development ) Rules, 2017 14 Jan 2021 · Disposed Authority Fullbench
- Complaint U/s. 63 of the Real Estate (Regulation & Development) Act, 2016 r/w. Rule 29 of the Karnataka Real Estate (Regulation and Development ) Rules, 2017 14 Jan 2021 · Disposed Authority Fullbench
- delay compensation 24 Feb 2021 · Disposed Authority Bench6
Documents
124 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹97.2 cr
- Construction
- ₹106.3 cr
- Total project cost
- ₹203.4 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station4.05 kmReliable
- Nearest railway station11.35 kmReliable
- Bus stops within 500 m5Caveat
Parks, shops, daily needs
- Supermarkets within 1 km6Caveat
- Parks within 1 km8Caveat
- Nearest lake / water body (≥2 ha)0.75 kmCaveat
Hospitals
- Nearest hospital0.51 kmCaveat
Schools
- Schools in pincode 560076 (UDISE+ census)85Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km12Caveat
- Median pupil-teacher ratio, schools within 1 km34.9 :1Caveat
- Schools with library + playground + ICT lab (1 km)8Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionHulimavu PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)26 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km1Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well10.8 m below groundCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)5.1 kmReliable
- Nearest sewage treatment plant0.69 kmCaveat
- Industrial zones within 1 km5Caveat
- Nearest airfield runway (any, incl. military)10.51 kmCaveat
- Nearest commercial-airport runway36.57 kmReliable
- Distance to runway approach-path proxy33.8 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.87146, 77.59784), 2026-10-24. Each figure's source and caveat are in the full report.