Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Nirmaanika ARIA

by Nirmaanika Projects · 68 homes · 0.76 acres · 1 tower · Bengaluru East

Upcoming Under construction, due Dec 2027. 50% built with 64% of the time used. 32% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
50% built

Due 31 Dec 2027. 64% of the time from RERA approval to the deadline has passed.

Built50%
Time used64%
How much is sold?46 left
32% booked

22 of 68 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
90 homes per acre

Similar projects within 3 km: 77 per acre. 46% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA5 Sep 2024
  2. Work started25 Sep 2024
  3. Today24 Oct 2026

    64% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2629%
Q4 2025-2635%
Q1 2026-2740%
Q2 2026-2750%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

22 booked46 leftQ2 2026-27

Still available: 35 × 2 BHK, 6 × 2.5 BHK, 5 × 3 BHK.

Booked, by type

2 BHK5 of 40
2.5 BHK6 of 12
3 BHK11 of 16

Booked, each quarter

Q3 2025-2615 of 68
Q4 2025-2615 of 68
Q1 2026-2717 of 68
Q2 2026-2722 of 68

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 BHK
646 sq ft
60 m² carpet · sizes 597–888 sq ft (12 at this size)
41 m² land share · 1 parking space
40 homes · 59% of the project
3 BHK
934 sq ft
87 m² carpet · sizes 893–952 sq ft (11 at this size)
57 m² land share · 1 parking space
16 homes · 24% of the project
2.5 BHK
722 sq ft
67 m² carpet · sizes 674–803 sq ft (3 at this size)
48 m² land share · 1 parking space
12 homes · 18% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Nirmaanika Aria4 floors

Nirmaanika Aria: 68 homes, 15 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project90
Typical within 3 km (85)77
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project46%
Typical within 3 km (84)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.76 acres

3,056 m²

Ground covered by buildings
54% of the land

1,658 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.00 per home

68 covered, 0 open

Built-up area, all floors
96,455 sq ft

8,961 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
Nirmaanika Projects
Type
Partnership Firm
PAN
AAVFN9636L
GSTIN
29AAVFN9636L1Z3

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹5.5 crBuilding and development ₹22.0 crTotal ₹27.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹2.7 cr₹4.7 cr
Q4 2025-26₹3.4 cr₹6.2 cr
Q1 2026-27₹1.1 cr₹6.8 lakh
Q2 2026-27₹4.9 cr₹1.7 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.94 kmReliable
  • Nearest railway station0.87 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km7Caveat
  • Nearest lake / water body (≥2 ha)2.03 kmCaveat

Hospitals

  • Nearest hospital0.32 kmCaveat

Schools

  • Schools in pincode 560067 (UDISE+ census)57Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km15Caveat
  • Median pupil-teacher ratio, schools within 1 km25.3 :1Caveat
  • Schools with library + playground + ICT lab (1 km)9Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km3Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km5Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)9.18 kmReliable
  • Nearest sewage treatment plant2.07 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)5.33 kmCaveat
  • Nearest commercial-airport runway20.79 kmReliable
  • Distance to runway approach-path proxy19.34 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (13.00407, 77.75956), 2026-10-24. Each figure's source and caveat are in the full report.