Nikoo Homes V - Phase - 2

by Bhartiya Urban Private Limited · 568 homes · 3.03 acres · 2 towers · Bengaluru North

Upcoming Under construction, due Jun 2030. 54% built with 44% of the time used. 81% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
54% built

Due 30 Jun 2030. 44% of the time from RERA approval to the deadline has passed.

Built54%
Time used44%
How much is sold?107 left
81% booked

461 of 568 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
188 homes per acre

Similar projects within 3 km: 75 per acre. 71% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 28 more about the builder's other projects.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?5 due so far
20% on time

Of its 16 RERA projects in Bengaluru Urban: 1 delivered on time, 3 late (after the date first promised), 1 past due with no completion filed, 11 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA27 Nov 2023
  2. Work started1 Oct 2024
  3. Today24 Oct 2026

    44% of the time to the deadline has passed.

  4. If it slips like a typical project1 Apr 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2644%
Q4 2025-2657%
Q1 2026-2751%
Q2 2026-2754%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower - 152%
Tower - 255%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

461 booked107 leftQ2 2026-27

Still available: 3 × 2.5 BHK, 88 × 3 BHK, 15 × 3.5 BHK, 1 × 2 BHK.

Booked, by type

2.5 BHK137 of 140
3 BHK196 of 284
3.5 BHK57 of 72
1 BHK2 of 2
2 BHK69 of 70

Booked, each quarter

Q3 2025-26245 of 568
Q4 2025-26414 of 568
Q1 2026-27433 of 568
Q2 2026-27461 of 568

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,015 sq ft
94 m² carpet · sizes 1,015–1,099 sq ft (72 at this size)
16 m² land share · 18 m² balcony/terrace · 1 parking space
284 homes · 50% of the project
2.5 BHK
845 sq ft
78 m² carpet · sizes 845–861 sq ft (72 at this size)
12 m² land share · 15 m² balcony/terrace · 1 parking space
140 homes · 25% of the project
3.5 BHK
1,209 sq ft
112 m² carpet
18 m² land share · 18 m² balcony/terrace · 1 parking space
72 homes · 13% of the project
2 BHK
707 sq ft
66 m² carpet
11 m² land share · 14 m² balcony/terrace · 1 parking space
70 homes · 12% of the project
1 BHK
524 sq ft
49 m² carpet
8 m² land share · 12 m² balcony/terrace · 1 parking space
2 homes · 0% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower - 138 floors
Tower - 238 floors

Tower - 1: 284 homes, 119 m tall, 3 basements · Tower - 2: 284 homes, 119 m tall, 3 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project188
Typical within 3 km (117)75
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project71%
Typical within 3 km (117)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.03 acres

12,246 m²

Ground covered by buildings
29% of the land

3,507 m²

Floor-area ratio
2.99

Floors built per unit of land: 2.99 m² of floors for each m² of land.

Parking
1.19 per home

676 covered, 0 open

Built-up area, all floors
11,39,800 sq ft

1,05,891 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 16 RERA projects of Bhartiya Urban on the map

Complaints to RERA about its other projects

28 complaints across 8 projects. The most complained about:

Show all 8 projects
  • Nikoo Homes 8, Bhartiya Garden Enclave, Phase-1 2 complaints
  • Nikoo Homes II West 1 complaint
  • Nikoo Homes II East 1 complaint

The company

Registered as
Bhartiya Urban Private Limited
Type
Company
Company number
U45200TN2008PTC103956

CIN or LLPIN, from the Registrar of Companies.

PAN
AAACZ3571A
GSTIN
29AAACZ3571A1ZF

Its other registrations on RERA Karnataka

15 registrations under this company
  • Nikoo Homes 9 Alpine Bhartiya Garden Hill Phase-2 PRM/KA/RERA/1251/309/PR/100926/008931 · approved 10 Sep 2026
  • Nikoo Homes 9, Alpine, Bhartiya Garden Hill Ph-1 PRM/KA/RERA/1251/309/PR/100926/008930 · approved 10 Sep 2026
  • Nikoo Homes 8, Bhartiya Garden Enclave, Phase-2 PRM/KA/RERA/1251/309/PR/070526/008629 · approved 7 May 2026
  • Nikoo Homes 8, Bhartiya Garden Enclave, Phase-1 PRM/KA/RERA/1251/309/PR/070526/008628 · approved 7 May 2026
  • Bhartiya Garden Estate Phase-3 PRM/KA/RERA/1251/309/PR/060925/008065 · approved 6 Sep 2025
  • Bhartiya Garden Estate Phase-2 PRM/KA/RERA/1251/309/PR/060925/008064 · approved 6 Sep 2025
  • Bhartiya Garden Estate Phase-1 PRM/KA/RERA/1251/472/PR/260825/008038 · approved 26 Aug 2025
  • Nikoo Homes VI - Phase-2 PRM/KA/RERA/1251/309/PR/160124/006550 · approved 16 Jan 2024
  • Nikoo Homes VI - Phase - 1 PRM/KA/RERA/1251/472/PR/160124/006543 · approved 16 Jan 2024
  • Nikoo Homes V - Phase - 1 PRM/KA/RERA/1251/309/PR/171123/006418 · approved 17 Nov 2023
  • Nikoo Homes IV PRM/KA/RERA/1251/472/PR/210731/004208 · approved 31 Jul 2021
  • Bhartiya Leela Residences PRM/KA/RERA/1251/309/PR/171015/000184 · approved 15 Oct 2017
  • Nikoo Homes II East PRM/KA/RERA/1251/309/PR/171014/000197 · approved 14 Oct 2017
  • Nikoo Homes II West PRM/KA/RERA/1251/309/PR/171014/000188 · approved 14 Oct 2017
  • Nikoo Homes I (Towers 1 - 6 & 10) PRM/KA/RERA/1251/309/PR/171014/000161 · approved 14 Oct 2017

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹36.7 crBuilding and development ₹495.6 crTotal ₹532.3 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹27.0 cr₹24.6 cr
Q4 2025-26₹30.7 cr₹40.7 cr
Q1 2026-27₹22.4 cr₹21.2 cr
Q2 2026-27₹58.0 cr₹18.4 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station9.59 kmReliable
  • Nearest railway station6.14 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km2Caveat
  • Parks within 1 km28Caveat
  • Nearest lake / water body (≥2 ha)0.43 kmCaveat

Hospitals

  • Nearest hospital0.9 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
  • Median pupil-teacher ratio, schools within 1 km11.7 :1Caveat
  • Schools with library + playground + ICT lab (1 km)2Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKothanur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)2.64 kmReliable
  • Nearest sewage treatment plant3.62 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)4.42 kmCaveat
  • Nearest commercial-airport runway13.26 kmReliable
  • Distance to runway approach-path proxy11.02 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (13.07933, 77.64210), 2026-10-24. Each figure's source and caveat are in the full report.