Navami Chamara Heights

by Navami Chamara Heights · 231 homes · 2.24 acres · 2 towers · Bengaluru North

Upcoming Under construction, due Jun 2028. 40% built with 61% of the time used. 62% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
40% built

Due 30 Jun 2028. 61% of the time from RERA approval to the deadline has passed.

Built40%
Time used61%
How much is sold?123 left
62% booked

204 of 327 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
103 homes per acre

Similar projects within 3 km: 93 per acre. 61% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started28 Feb 2024
  2. Approved by RERA6 Mar 2024
  3. Today24 Oct 2026

    61% of the time to the deadline has passed.

  4. If it slips like a typical project1 Apr 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q4 2025-2627%
Q1 2026-2730%
Q2 2026-2740%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A65%
Tower B30%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

204 booked123 leftQ2 2026-27

Still available: 17 × 2.5BHK, 20 × 2BHK, 86 × 3BHK.

Booked, by type

2.5BHK38 of 55
2BHK34 of 54
3BHK132 of 218

Booked, each quarter

Q4 2025-26172 of 327
Q1 2026-27183 of 327
Q2 2026-27204 of 327

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK
1,063 sq ft
99 m² carpet · sizes 1,028–1,063 sq ft (109 at this size)
30 m² land share · 34 m² balcony/terrace · 1 parking space
218 homes · 67% of the project
2.5BHK
876 sq ft
81 m² carpet
25 m² land share · 28 m² balcony/terrace · 1 parking space
55 homes · 17% of the project
2BHK
779 sq ft
72 m² carpet
22 m² land share · 26 m² balcony/terrace · 1 parking space
54 homes · 17% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A30 floors
Tower B30 floors

Tower A: 165 homes, 1 basement · Tower B: 162 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project103
Typical within 3 km (17)93
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project61%
Typical within 3 km (17)48%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.24 acres

9,055 m²

Ground covered by buildings
39% of the land

3,545 m²

Floor-area ratio
4.20

Floors built per unit of land: 4.20 m² of floors for each m² of land.

Parking
1.17 per home

271 covered, 0 open

Built-up area, all floors
4,27,531 sq ft

39,719 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
Navami Chamara Heights
Type
Partnership Firm
PAN
AAVFN0937C
GSTIN
29AAVFN0937C1Z0
Website
www.navamibuilders.com

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹39.1 crBuilding and development ₹109.0 crTotal ₹148.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q4 2025-26₹9.0 cr₹9.8 cr
Q1 2026-27₹11.0 cr₹7.6 cr
Q2 2026-27₹14.1 cr₹10.2 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.05 kmReliable
  • Nearest railway station3.22 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km14Caveat
  • Nearest lake / water body (≥2 ha)1.2 kmCaveat

Hospitals

  • Nearest hospital0.48 kmCaveat

Schools

  • Schools in pincode 560056 (UDISE+ census)59Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km14Caveat
  • Median pupil-teacher ratio, schools within 1 km23.6 :1Caveat
  • Schools with library + playground + ICT lab (1 km)9Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionJnanabharathi PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)11 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km2Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)17.82 kmReliable
  • Nearest sewage treatment plant2.72 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)18.67 kmCaveat
  • Nearest commercial-airport runway35.07 kmReliable
  • Distance to runway approach-path proxy29.29 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.94673, 77.48202), 2026-10-24. Each figure's source and caveat are in the full report.