RERA project · Residential/Group Housing
MILLENIA MUTHANALLUR
by Nambiar Enterprises LLP · 604 homes · 3.84 acres · 4 towers · Anekal
Delivered on time Completed: the builder filed for completion on 6 May 2026, by the date it promised.
At a glance
The builder filed for completion on 6 May 2026, by the date it promised.
523 of 604 homes, as the builder reported for Q4 2025-26.
Similar projects across the city: 76 per acre. 74% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started4 Nov 2021
- Approved by RERA2 Feb 2022
- Completion filed6 May 2026
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q4 2025-26
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 20 × 2.5BHK, 49 × 2BHK, 12 × 3BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower A: 190 homes, 1 basement · Tower B: 120 homes, 1 basement · Tower C: 154 homes, 1 basement · Tower D: 140 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
- Air Conditioning And incerntion
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.84 acres
- Ground covered by buildings
- 26% of the land
15,530 m²
4,015 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Nambiar Enterprises LLP
- Type
- Partnership Firm
- PAN
- AAPFN4989G
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/220202/004665 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q4 2025-26 update
Complaints to RERA about this project
None on RERA Karnataka.
Documents
171 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹5.4 cr
- Construction
- ₹133.5 cr
- Total project cost
- ₹139.0 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹25.2 cr | ₹20.3 cr |
| Q4 2025-26 | ₹38.9 cr | ₹22.5 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.