Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

MIGHTY YUVA

by MIGHTY HOMES · 68 homes · 0.92 acres · 1 tower · Bengaluru East

Upcoming Under construction, due Sep 2027. 80% built with 58% of the time used. 7% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
80% built

Due 30 Sep 2027. 58% of the time from RERA approval to the deadline has passed.

Built80%
Time used58%
How much is sold?63 left
7% booked

5 of 68 homes, as the builder reported for Q4 2025-26.

How crowded is it?About the same
74 homes per acre

Similar projects within 3 km: 80 per acre. 45% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Apr 2025
  2. Approved by RERA1 Jul 2025
  3. Today24 Oct 2026

    58% of the time to the deadline has passed.

  4. If it slips like a typical project1 Jul 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2656%
Q4 2025-2661%
Q1 2026-2775%
Q2 2026-2780%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

5 booked63 leftQ4 2025-26

Still available: 31 × 2 BHK, 28 × 3 BHK, 4 × 4 BHK.

Booked, by type

2 BHK1 of 32
3 BHK4 of 32
4 BHK0 of 4

Booked, each quarter

Q3 2025-264 of 68
Q4 2025-265 of 68

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
  • 1,019 sq ft4 homes94.7 m²
  • 1,040 sq ft4 homes96.6 m²
  • 1,046 sq ft4 homes97.2 m²
  • 1,060 sq ft4 homes98.5 m²
  • and 16 homes in other sizes
Typically 61 m² land share · 47 m² balcony/terrace · 1 parking space
32 homes · 47% of the project
2 BHK
  • 720 sq ft4 homes66.9 m²
  • 739 sq ft4 homes68.7 m²
  • 759 sq ft4 homes70.5 m²
  • 772 sq ft4 homes71.7 m²
  • and 16 homes in other sizes
Typically 45 m² land share · 34 m² balcony/terrace · 1 parking space
32 homes · 47% of the project
4 BHK
  • 1,326 sq ft4 homes123.2 m²
Typically 74 m² land share · 49 m² balcony/terrace · 1 parking space
4 homes · 6% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Mighty Yuva4 floors

Mighty Yuva: 68 homes, 15 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project74
Typical within 3 km (81)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project45%
Typical within 3 km (80)62%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.92 acres

3,730 m²

Ground covered by buildings
55% of the land

2,043 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.10 per home

75 covered, 0 open

Built-up area, all floors
1,12,149 sq ft

10,419 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of M/s.Mighty Homes on the map

The company

Registered as
MIGHTY HOMES
Type
Partnership Firm
PAN
AAXFM0372Q
GSTIN
29AAXFM0372Q1Z9

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹1.2 crBuilding and development ₹25.9 crTotal ₹27.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹1.5 cr₹1.0 cr
Q4 2025-26₹56.5 lakh₹14.3 lakh
Q1 2026-27₹2.1 cr₹2.1 cr
Q2 2026-27₹2.4 cr₹1.8 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.74 kmReliable
  • Nearest railway station3.77 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km6Caveat
  • Nearest lake / water body (≥2 ha)0.61 kmCaveat

Hospitals

  • Nearest hospital1.06 kmCaveat

Schools

  • Schools in pincode 560067 (UDISE+ census)57Caveat
  • Median pupil-teacher ratio, schools within 1 km26.2 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well60.8 m below groundCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.28 kmReliable
  • Nearest sewage treatment plant1.05 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)7.07 kmCaveat
  • Nearest commercial-airport runway17.94 kmReliable
  • Distance to runway approach-path proxy16.77 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.02874, 77.75047), 2026-10-24. Each figure's source and caveat are in the full report.