Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

MIDORI

by TATTVAM VENTURES · 117 homes · 5.43 acres · 11 towers · Anekal

Upcoming Under construction, due Nov 2028. 20% built with 41% of the time used. 17% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
20% built

Due 30 Nov 2028. 41% of the time from RERA approval to the deadline has passed.

Built20%
Time used41%
How much is sold?97 left
17% booked

20 of 117 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
22 homes per acre

Similar projects within 3 km: 71 per acre. 15% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
100% on time

Of its 2 RERA projects in Bengaluru Urban: 1 delivered on time, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Apr 2025
  2. Approved by RERA16 May 2025
  3. Today24 Oct 2026

    41% of the time to the deadline has passed.

  4. If it slips like a typical project1 Sep 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-269%
Q4 2025-2618%
Q1 2026-2716%
Q2 2026-2720%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block-A20%
Block-B20%
Block-C20%
Block-D20%
Block-E20%
Block-F20%
Block-G20%
Block-H20%
Block-I20%
Block-J20%
Block-K20%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

20 booked97 leftQ2 2026-27

Still available: 61 × 3B 3T, 7 × 3B 3T M+HO, 20 × 3B 3T HO, 5 × 4B 3T, 4 × 3B3T.

Booked, by type

3B 3T15 of 76
3B 3T M+HO1 of 8
3B 3T HO0 of 20
4B 3T3 of 8
3B3T0 of 4
2B 2T1 of 1

Booked, each quarter

Q3 2025-2614 of 117
Q4 2025-2614 of 117
Q1 2026-2718 of 117
Q2 2026-2720 of 117

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3B 3T
  • 1,858 sq ft16 homes172.6 m²
  • 1,328 sq ft4 homes123.4 m²
  • 1,365 sq ft4 homes126.8 m²
  • 1,372 sq ft4 homes127.5 m²
  • and 48 homes in other sizes
Typically 123 m² land share · 22 m² balcony/terrace · 1 parking space
76 homes · 65% of the project
3B 3T HO
  • 1,949 sq ft16 homes181.1 m²
  • 1,922 sq ft4 homes178.6 m²
Typically 158 m² land share · 22 m² balcony/terrace · 1 parking space
20 homes · 17% of the project
3B 3T M+HO
  • 1,931 sq ft4 homes179.4 m²
  • 1,984 sq ft4 homes184.3 m²
Typically 167 m² land share · 34 m² balcony/terrace · 1 parking space
8 homes · 7% of the project
4B 3T
  • 1,635 sq ft4 homes151.9 m²
  • 1,700 sq ft4 homes157.9 m²
Typically 143 m² land share · 28 m² balcony/terrace · 1 parking space
8 homes · 7% of the project
3B3T
  • 1,367 sq ft4 homes127.0 m²
Typically 116 m² land share · 21 m² balcony/terrace · 1 parking space
4 homes · 3% of the project
2B 2T
  • 1,370 sq ft1 home127.3 m²
Typically 98 m² land share · 1 parking space
1 home · 1% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block-A3 floors
Block-B3 floors
Block-C3 floors
Block-D3 floors
Block-E3 floors
Block-F3 floors
Block-G3 floors
Block-H3 floors
Block-I3 floors
Block-J3 floors
Block-K3 floors

Block-A: 4 homes, 14 m tall, 1 basement · Block-B: 8 homes, 14 m tall, 1 basement · Block-C: 12 homes, 14 m tall, 1 basement · Block-D: 12 homes, 14 m tall, 1 basement · Block-E: 4 homes, 14 m tall, 1 basement · Block-F: 16 homes, 14 m tall, 1 basement · Block-G: 12 homes, 14 m tall, 1 basement · Block-H: 16 homes, 14 m tall, 1 basement · Block-I: 16 homes, 14 m tall, 1 basement · Block-J: 16 homes, 14 m tall, 1 basement · Block-K: 1 home, 14 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project22
Typical within 3 km (65)71
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project15%
Typical within 3 km (65)62%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
5.43 acres

21,979 m²

Ground covered by buildings
85% of the land

18,682 m²

Floor-area ratio
1.27

Floors built per unit of land: 1.27 m² of floors for each m² of land.

Parking
1.27 per home

149 covered, 0 open

Built-up area, all floors
4,42,396 sq ft

41,100 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of TATTVAM VENTURES on the map

The company

Registered as
TATTVAM VENTURES
Type
Partnership Firm
PAN
AAQFT1885Q
GSTIN
29AAQFT1885Q1ZX
Website
https://www.woodsvale.in

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development), including Royale Developers, Royale Properties.

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹5.1 crBuilding and development ₹106.0 crTotal ₹111.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹2.0 cr₹1.4 cr
Q4 2025-26₹61.5 lakh₹43.1 lakh
Q1 2026-27₹3.6 cr₹2.5 cr
Q2 2026-27₹1.6 cr₹1.1 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station11.92 kmReliable
  • Nearest railway station9.46 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km3Caveat
  • Nearest lake / water body (≥2 ha)0.24 kmCaveat

Hospitals

  • Nearest hospital2.75 kmCaveat

Schools

  • Schools in pincode 562125 (UDISE+ census)91Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)15.38 kmReliable
  • Nearest sewage treatment plant8.61 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)12.24 kmCaveat
  • Nearest commercial-airport runway34.28 kmReliable
  • Distance to runway approach-path proxy32.04 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.88549, 77.79011), 2026-10-24. Each figure's source and caveat are in the full report.