RERA project · Residential/Group Housing
Mantri Webcity2A
by Mantri Developers Private Limited · 588 homes · 5.30 acres · 4 towers · Bengaluru South
Past due, no completion filed Past its deadline of 28 Feb 2021, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 28 Feb 2021, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 76% of the land is left open.
Complaints to RERA about this project. 93 more about the builder's other projects.
The RERA page doesn't say.
Of its 18 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 14 past due with no completion filed, 1 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started4 Mar 2013
- Approved by RERA15 Oct 2017
- First promised28 Feb 2020
The date the builder gave at registration.
- Deadline (extended)28 Feb 2021
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
F: 147 homes, 1 basement · G: 147 homes, 1 basement · H: 147 homes, 1 basement · J: 147 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.30 acres
- Ground covered by buildings
- 14% of the land
21,448 m²
2,932 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 18 RERA projects of Mantri Developers on the map
Complaints to RERA about its other projects
93 complaints across 6 projects. The most complained about:
- Mantri Webcity3A 25 complaints
- Mantri Webcity3B 24 complaints
- Mantri Webcity2B 23 complaints
- Mantri Webcity3C 10 complaints
- Mantri Centrium 10 complaints
Show all 6 projects
- mantri webcity 2B 1 complaint
The company
- Registered as
- Mantri Developers Private Limited
- Type
- Company
- Company number
- U70102KA1990PTC027924
- PAN
- AAACG4009N
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171015/000608 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- REFUND OF DOWN PAYMENT WITH 100% ASSURED RETURN UNDER BUYBACK, CLOSURE OF HOME LOAN WITH PNBHFL, PAYMENT OF INTEREST, REFUND OF EMIs PAID TO PNBHFL, COMPENSATION 11 Feb 2019 · Disposed Authority Fullbench
- Possession dates are registered wrongly with RERA for MANTRI WEBCITY 2A 20 Feb 2019 · Disposed Ao
- REFUND OF DOWN PAYMENT WITH 100% ASSURED RETURN UNDER BUYBACK, CLOSURE OF HOME LOAN WITH PNBHFL, PAYMENT OF INTEREST, REFUND OF EMIs PAID TO PNBHFL, COMPENSATION 5 Mar 2019 · Disposed Ao
- Delay of Possession and Promised Refund 4 Apr 2019 · Disposed Ao
- Complaint against Mantri Web City2A project developed by Mantri Developers PVT limited, for non refund of our investment towards purchase of the apartment G1002 27 May 2019 · Disposed Ao
- Seeking a complete refund of the amount paid along with 18% interest due to unwarranted delay in possession of the flat 29 May 2019 · Disposed Ao
- Mantri Developers Private Limited not refunding due amount as per MOU 30 May 2019 · Disposed Ao
- Compensation for delayed handover of apartment 18 Jun 2019 · Disposed Ao
- Non Delivery of Apartment, Delayed Compensation, Damages for Mental Agony, Mental Torture and Unfair Trade Practice etc 4 Jul 2019 · Disposed Ao
- Complaint against Mantri Developers for Mantri Webcity 2A - Refund, honour assured returns, close all PRE EMIs, close loan and compensate. 8 Jul 2019 · Disposed Ao
- Refund of PRE-EMI, Delayed compensation and others 9 Jul 2019 · Disposed Ao
- Failed to return assured buy back amount, project delayed, not paying back pre EMI, 17 Jul 2019 · Disposed Ao
- Non Delivery of Apartment, Delayed Compensation, Interest Refund, Damages for Mental Agony, Mental Torture and Unfair Trade Practice 18 Jul 2019 · Disposed Ao
- Apt Possession, Delayed compensation, Refund of Pre-Emi, damages for deficiency of service, mental agony, harassment and unfair trade practice. 21 Jul 2019 · Disposed Ao
- Seeking a complete refund of the amount paid along with the interest due to unwarranted delay in possession of the flat 16 Aug 2019 · Disposed Ao
- Non Delivery of Apartment, Non payment of Pre-EMI, Delayed Compensation, Interest Refund, Damages for Mental Agony, Mental Torture and Unfair Trade Practice 17 Aug 2019 · Disposed Ao
- Mantri Webcity G1205 - Delay in possession + No preEmi + No buy scheme closur 18 Aug 2019 · Disposed Ao
- Refund of sale consideration, Payment of assured sum of money, closure of loan, compensation for Non Delivery of Apartment, Delayed Compensation, Damages for Mental Agony, Mental Torture and Unfair Tr 23 Aug 2019 · Disposed Ao
- REFUND OF ADVANCE SALE CONSIDERATION AND COMPENSATION FOR LOSS 14 Jan 2020 · Disposed Authority Bench5
- Possession with OC and delayed compensation 16 Jan 2020 · Disposed Authority Bench5
- Delay Compensation, Possession with OC along with all amenities 29 Feb 2020 · Disposed Authority Bench5
- Possession of Apartment with OC, Delay Compensation 4 Mar 2020 · Disposed Authority Bench5
- Delayed compensation, Possession and Occupancy Certificate 10 Mar 2020 · Disposed Authority Bench5
- Inordinate delay in handing over of the possession of house No. J-1306 at Mantri Webcity2A on Hennur Road, Bangalore 13 Mar 2020 · Disposed Ao
- Delayed compensation, Possession along with OC and amenities 14 Mar 2020 · Disposed Ao
- Delay Compensation, OC and Possession with all amenities 2 Apr 2020 · Disposed Authority Bench5
- Delayed Compensation until Possession with amenities and Occupancy Certificate 3 Apr 2020 · Disposed Ao
- Compensation for delayed possession, handing over of the possession along with Occupancy Certificate and All amenities 22 May 2020 · Disposed Authority Bench5
- Exit from project and refund of money along with interest and other expenses 3 Jul 2020 · Disposed Authority Bench5
- Delayed Compensation and Exit from project with bank loan closure and refund of all interest and expense 1 Aug 2020 · Disposed Authority Bench5
- Delay compensation until possession along with amenities and Occupancy Certificate 9 Aug 2020 · Disposed Authority Bench5
- Refund of PRE-EMI installment, interest, delay compensation and payment of 2X amount as per the scheme 15 Aug 2020 · Disposed Authority Bench5
- possession, delayed compensation until handing over possession along with Occupancy Certificate and all amenities 15 Aug 2020 · Disposed Authority Bench5
- refund of all money and delay compensation, refund of money with interest, closure of bank loan etc 12 Sep 2020 · Disposed Authority Bench5
- delay compensation, possession and occupancy certificate 18 Sep 2020 · Disposed Authority Bench5
- Delay compensation, possession and occupancy certificate 18 Sep 2020 · Disposed Authority Bench5
- Delayed Compensation, Possession and Occupancy certificate 18 Sep 2020 · Disposed Authority Bench5
- Possession, Delay compensation and Occupancy Certificate 18 Sep 2020 · Disposed Authority Bench5
- Delayed compensation, refund of money, closure of loan 24 Sep 2020 · Disposed Ao
- Possession delayed over three years and no construction is going on 7 Jan 2021 · Disposed Authority Bench5
- Requesting for Refund/Compensation for our losses occured due to Mantri's inability to give us our flat. 4 Feb 2021 · Disposed Authority Bench5
- Delayed compensation until repayment, closure of Bank Loan and NOC from Bank 9 Feb 2021 · Disposed Authority Bench5
- Project delayed. Hence, seeking cancellation of the Sale Agreement and Construction Agreement and for refund of money along with Interest 30 Jul 2021 · Disposed Authority Bench5
- Reimbursement of pre EMI for Sharad Mantri 30 Aug 2021 · Disposed Authority Bench6
- Complaint under Section 31 r/w Section 18 and 19 seeking refund and interest 28 Apr 2022 · Disposed Authority Bench5
- Refund of Booking amount by Manti Developer for Manti Webcity 20 Jun 2022 · Disposed Authority Bench5
- Refund of money paid against flat J-403 due to delay in handing over the flat as per agreed timeline 6 Jul 2022 · Disposed Authority Bench5
- Adherence of buyback scheme and loan exit 5 Sep 2022 · Disposed Authority Bench5
- Refund of the amount invested plus the buyback amount with interest 15 Sep 2022 · Disposed Authority Bench5
- Refund with interest 15 Sep 2022 · Disposed Authority Bench5
- DELAY COMPENSATION .. 3 Nov 2022 · Disposed Authority Bench5
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund 7 Nov 2022 · Disposed Authority Bench4
- Refund of amount with assured returns and cancellation of the loan 15 Nov 2022 · Disposed Authority Bench5
- Refund 17 Jan 2023 · Disposed Authority Bench5
- Refund 17 Jan 2023 · Disposed Authority Bench5
- Refund 4 Mar 2023 · Disposed Authority Bench5
- Refund Booking amount 15 Mar 2023 · Disposed Authority Bench6
- Refund of amount with interest 3 May 2023 · Disposed Authority Bench5
- Compensation 15 Nov 2023 · Disposed Ao
- Compensation 15 Nov 2023 · Disposed Ao
- Compensation 15 Nov 2023 · Disposed Ao
- Refund of money with guaranteed profit and closure of loan 16 Feb 2024 · Disposed Authority Bench5
- delay in project, delivery as promised in agreement 4 Jun 2024 · Disposed Authority Bench5
- Refund 12 Aug 2024 · Disposed Authority Bench5
- for delivery of apartment bearing No.J 806 and for the payment of interest on delay period . 22 Aug 2024 · Disposed Authority Fullbench
- a complaint against builders and landowners of the Mantri Webcity real estate project, citing delays in physical delivery, false advertisements, payment and reimbursement problems, inadequacies in ser 7 Jan 2025 · Disposed Authority Fullbench
- Complaint under Section 31 of RERA 11 Mar 2025 · Disposed Authority Fullbench
- delay in project, delivery as promised in agreement 22 Jul 2025 · Under Enquiry Authority Fullbench
- Handover of possession and registration of sale deed. 14 Jul 2026 · Under Enquiry Authority Fullbench
- Handover of possession and registration of sale deed. 14 Jul 2026 · Under Enquiry Authority Fullbench
- interest on delay period 25 Aug 2026 · Under Enquiry Authority Fullbench
Documents
79 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹100.2 cr
- Construction
- ₹180.3 cr
- Total project cost
- ₹280.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.