Past due, no completion filed Past its deadline of 31 Dec 2022, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2022, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 76% of the land is left open.
Complaints to RERA about this project. 49 more about the builder's other projects.
The RERA page doesn't say.
Of its 18 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 14 past due with no completion filed, 1 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started27 Apr 2015
- Approved by RERA19 Oct 2017
- First promised29 Jan 2020
The date the builder gave at registration.
- Deadline (extended)31 Dec 2022
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
N: 112 homes, 3 basements · O: 112 homes, 3 basements · P: 112 homes, 3 basements · Q: 112 homes, 3 basements · R: 112 homes, 3 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 19.59 acres
- Ground covered by buildings
- 4% of the land
79,287 m²
3,380 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 18 RERA projects of Mantri Developers on the map
Complaints to RERA about its other projects
- Mantri Serenity4 32 complaints
- Mantri Serenity3 11 complaints
- Mantri Serenity1 6 complaints
The company
- Registered as
- CASTLES VISTA PRIVATE LIMITED
- Type
- Company
- PAN
- AABCL0438P
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171019/000504 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Compensation for Delay in Possession 18 Feb 2019 · Disposed Ao
- complete refund of booking amount 17 Apr 2019 · Disposed Ao
- Seeking for delayed compensation as per RERA 9 May 2019 · Disposed Ao
- Delay in possession of flat no.N501 11 Nov 2019 · Disposed Ao
- Delay of more than 4 years - compensation needed 4 Dec 2019 · Disposed Authority Bench5
- Delay compensation until Possession and Occupancy Certificate 28 Sep 2020 · Disposed Authority Bench5
- Delayed compensation until possession and occupancy certificate 4 Oct 2020 · Disposed Authority Bench6
- Delay compensation until possession and Occupancy Certificate 10 Oct 2020 · Disposed Authority Bench5
- Delay in handover/possession and promised Refund 18 Oct 2020 · Disposed Authority Bench5
- Delay compensation until Occupancy Certificate and Possession by Sale Deed 29 Oct 2020 · Disposed Authority Bench5
- Delay compensation until Occupancy Certificate and Possession with Sale Deed 1 Nov 2020 · Disposed Authority Bench5
- Delay of Possession/Hand over and Promised Refund 1 Nov 2020 · Disposed Authority Bench5
- Delay compensation, refund of arrear of pre-emi and possession of the apartment 12 Nov 2020 · Disposed Authority Bench5
- Compensation for Delay until Occupancy Certificate and possession with Sale Deed 19 Nov 2020 · Disposed Authority Bench5
- Delay in possession/handover and promised refund 20 Nov 2020 · Disposed Authority Bench5
- Compensation for Delay until possession and occupancy certificate 22 Nov 2020 · Disposed Authority Bench5
- delay compensation until Occupancy and possession 6 Dec 2020 · Disposed Authority Bench5
- Delay Compensation until possession with Occupancy Certificate along with amenities 15 Dec 2020 · Disposed Authority Bench5
- delay compensation until sale deed and occupancy certificate 15 Dec 2020 · Disposed Authority Bench5
- Delayed compensation until possession and sale deed and amenities 29 Jan 2021 · Disposed Authority Bench5
- Delay compensation and possession of Apartment with all amenities and Occupancy Certificate 22 Mar 2021 · Disposed Authority Bench5
- Project not completed and not handed over 30 Apr 2022 · Disposed Authority Bench4
- Refund 12 Dec 2022 · Disposed Authority Bench5
- Refund 12 Dec 2022 · Disposed Authority Bench5
- Denial of possession 10 Jan 2023 · Disposed Authority Fullbench
- COMPLAINT UNDER SECTION 31 OF THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 for Refund, Compensation and Directions 21 Jan 2023 · Disposed Authority Bench5
- Refund Amount 13 May 2024 · Disposed Authority Bench4
- Refund of amount with interest 2 Jan 2025 · Disposed Authority Fullbench
- Delay in possession due to non-availability of E-Khata - Flat No. J-1601, Mantri Serenity 21 Apr 2026 · Under Enquiry Authority Bench4
Documents
87 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹108.7 cr
- Construction
- ₹265.0 cr
- Total project cost
- ₹373.7 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.