Neighborhood IntelOpen on the map

RERA project · Plotted Development

Mantri Courtyard Phase 5

by Primus Lifespaces Pvt Ltd · 1.62 acres · Bengaluru South

Delivered on time Completed: the builder filed for completion on 19 Nov 2022, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 19 Nov 2022, by the date it promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Unknown
Not known

The RERA page gives no usable land area.

Any complaints?See the list
1 complaint

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?16 due so far
6% on time

Of its 18 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 14 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started1 Oct 2020
  2. Approved by RERA25 Nov 2020
  3. Completion filed19 Nov 2022

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How crowded is it?

Land left open

This project50%
Typical within 3 km (7)50%
Typical in the city (730)46%

The share of the land not built on, which includes roads.

Land
1.62 acres

6,576 m²

Plot area (the sites)
50% of the land

3,292 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 18 RERA projects of Mantri Developers on the map

Complaints to RERA about its other projects

The company

Registered as
Primus Lifespaces Pvt Ltd
Type
Company
Company number
U45201KA2006PTC039176

CIN or LLPIN, from the Registrar of Companies.

PAN
AAFCA9062J

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹2.0 cr
Construction
₹2.6 cr
Total project cost
₹4.6 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.94 kmReliable
  • Nearest railway station7.02 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)0.82 kmCaveat

Hospitals

  • Nearest hospital2.52 kmCaveat

Schools

  • Schools in pincode 560062 (UDISE+ census)66Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionThalaghattapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km2Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well8.2 m below groundCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.57 kmReliable
  • Nearest sewage treatment plant4.87 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)16.67 kmCaveat
  • Nearest commercial-airport runway39.83 kmReliable
  • Distance to runway approach-path proxy35.53 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.86817, 77.52427), 2026-10-24. Each figure's source and caveat are in the full report.