Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

MANITO NORTHLITE

by Manito Northlite · 10 homes · 0.37 acres · Bengaluru North

Delivered late Completed: the builder filed for completion on 1 Oct 2020, 990 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 1 Oct 2020, 990 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
27 homes per acre

Similar projects across the city: 76 per acre. 40% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started15 Jan 2015
  2. Approved by RERA31 Oct 2017
  3. Completion filed1 Oct 2020

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

This project's RERA page has no flat-by-flat list, so these are the builder's summary figures, exactly as filed. Builders often give the carpet area of all homes of a type together there: a figure marked "in all" covers every one of them, not one home.

Apartment
7,976 sq ft in all
741.0 m² carpet for all 10 homes together, as filed
79.0 m² balcony in all
10 homes · 100% of the project

Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by.

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project27
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project40%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.37 acres

1,482 m²

Ground covered by buildings
60% of the land

889 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
Manito Northlite
Type
Partnership Firm
PAN
ABAFM5071A

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹75.0 lakh
Construction
₹5.5 cr
Total project cost
₹6.2 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.