Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

MANA VISTA

by MANA PROJECTS PRIVATE LIMITED · 379 homes · 5.38 acres · 3 towers · Anekal

Upcoming Under construction, due Dec 2030. 23% built with 28% of the time used. 31% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
23% built

Due 31 Dec 2030. 28% of the time from RERA approval to the deadline has passed.

Built23%
Time used28%
How much is sold?261 left
31% booked

118 of 379 homes, as the builder reported for Q2 2026-27.

How crowded is it?About the same
70 homes per acre

Similar projects within 3 km: 68 per acre. 83% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 8 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
0% on time

Of its 8 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 6 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA15 Mar 2025
  2. Work started1 Jul 2025
  3. Today24 Oct 2026

    28% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-264%
Q4 2025-269%
Q1 2026-2712%
Q2 2026-2723%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower 119%
Tower 219%
Tower 320%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

118 booked261 leftQ2 2026-27

Still available: 44 × 2BHK + STUDY - 2T, 32 × 2BHK-2T, 54 × 3BHK-2T, 96 × 3BHK-3T, 35 × EWS.

Booked, by type

2BHK + STUDY - 2T35 of 79
2BHK-2T3 of 35
3BHK-2T24 of 78
3BHK-3T56 of 152
EWS0 of 35

Booked, each quarter

Q3 2025-2677 of 379
Q4 2025-26101 of 379
Q1 2026-27113 of 379
Q2 2026-27118 of 379

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK-3T
978 sq ft
91 m² carpet · sizes 975–1,009 sq ft (30 at this size)
49 m² land share · 8 m² balcony/terrace · 1 parking space
152 homes · 40% of the project
2BHK + STUDY - 2T
741 sq ft
69 m² carpet · sizes 741–769 sq ft (29 at this size)
37 m² land share · 3 m² balcony/terrace · 1 parking space
79 homes · 21% of the project
3BHK-2T
899 sq ft
84 m² carpet · sizes 896–920 sq ft (33 at this size)
44 m² land share · 4 m² balcony/terrace · 1 parking space
78 homes · 21% of the project
2BHK-2T
792 sq ft
74 m² carpet · sizes 792–826 sq ft (9 at this size)
41 m² land share · 8 m² balcony/terrace · 1 parking space
35 homes · 9% of the project
EWS
173 sq ft
16 m² carpet · sizes 161–186 sq ft (18 at this size)
8 m² land share · 28 m² balcony/terrace · 0 parking spaces
35 homes · 9% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 18 floors
Tower 28 floors
Tower 314 floors

Tower 1: 84 homes, 27 m tall, 2 basements · Tower 2: 74 homes, 27 m tall, 2 basements · Tower 3: 221 homes, 45 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project70
Typical within 3 km (94)68
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project83%
Typical within 3 km (94)66%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
5.38 acres

21,752 m²

Ground covered by buildings
17% of the land

3,691 m²

Floor-area ratio
2.00

Floors built per unit of land: 2.00 m² of floors for each m² of land.

Parking
1.56 per home

583 covered, 8 open

Built-up area, all floors
3,64,627 sq ft

33,875 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 8 RERA projects of MANA PROJECTS PRIVATE LIMITED on the map

Complaints to RERA about its other projects

The company

Registered as
MANA PROJECTS PRIVATE LIMITED
Type
Company
Company number
U45202KA2009PTC049111

CIN or LLPIN, from the Registrar of Companies.

PAN
AAFCM8997G
GSTIN
29AAFCM8997G1ZN
Website
manaprojects.com

Its other registrations on RERA Karnataka

7 registrations under this company
  • MANA VERDANT TERRACES PRM/KA/RERA/1251/446/PR/041225/008303 · approved 4 Dec 2025
  • MANA DALE SOUTH -1 PRM/KA/RERA/1251/446/PR/220125/007417 · approved 22 Jan 2025
  • MANA DALE PRM/KA/RERA/1251/446/PR/091123/006409 · approved 9 Nov 2023
  • MANA VERDANT PRM/KA/RERA/1251/309/PR/260523/005947 · approved 26 May 2023
  • MACASA EMERALD PRM/KA/RERA/1251/446/PR/101122/005450 · approved 10 Nov 2022
  • UBER VERDANT - II PRM/KA/RERA/1251/446/PR/190525/002575 · approved 25 May 2019
  • MANA TROPICALE PRM/KA/RERA/1251/446/PR/171015/000317 · approved 15 Oct 2017

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹14.0 crBuilding and development ₹201.0 crTotal ₹215.0 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹8.1 cr₹3.8 cr
Q4 2025-26₹13.8 cr₹10.3 cr
Q1 2026-27₹8.7 cr₹7.6 cr
Q2 2026-27₹27.5 cr₹18.1 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station4.45 kmReliable
  • Nearest railway station3.43 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km2Caveat
  • Nearest lake / water body (≥2 ha)0.7 kmCaveat

Hospitals

  • Nearest hospital2.18 kmCaveat

Schools

  • Schools in pincode 560035 (UDISE+ census)45Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km2Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)5.8 kmReliable
  • Nearest sewage treatment plant2.08 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)8.37 kmCaveat
  • Nearest commercial-airport runway34.54 kmReliable
  • Distance to runway approach-path proxy33.93 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.87713, 77.69876), 2026-10-24. Each figure's source and caveat are in the full report.