Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

MANA DALE SOUTH -1

by MANA PROJECTS PVT LTD · 257 homes · 6.98 acres · 2 towers · Bengaluru East

Upcoming Under construction, due Nov 2029. 47% built with 36% of the time used. 51% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
47% built

Due 30 Nov 2029. 36% of the time from RERA approval to the deadline has passed.

Built47%
Time used36%
How much is sold?126 left
51% booked

131 of 257 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
37 homes per acre

Similar projects within 3 km: 69 per acre. 96% of the land is left open.

Any complaints?See the list
2 complaints

Complaints to RERA about this project. 6 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
0% on time

Of its 8 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 6 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started2 Jan 2025
  2. Approved by RERA22 Jan 2025
  3. Today24 Oct 2026

    36% of the time to the deadline has passed.

  4. If it slips like a typical project1 Sep 2030

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2613%
Q4 2025-2628%
Q1 2026-2735%
Q2 2026-2747%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

South Tower 148%
South Tower 248%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

131 booked126 leftQ2 2026-27

Still available: 51 × 2 BHK, 25 × 3 BHK, 50 × NA.

Booked, by type

2 BHK0 of 51
3 BHK131 of 156
NA0 of 50

Booked, each quarter

Q3 2025-2666 of 257
Q4 2025-2679 of 257
Q1 2026-27105 of 257
Q2 2026-27131 of 257

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,027 sq ft
95 m² carpet · sizes 930–1,074 sq ft (53 at this size)
39 m² land share · 10 m² balcony/terrace · 1 parking space
156 homes · 61% of the project
2 BHK
832 sq ft
77 m² carpet · sizes 832–1,006 sq ft (50 at this size)
32 m² land share · 9 m² balcony/terrace · 1 parking space
51 homes · 20% of the project
NA
175 sq ft
16 m² carpet
7 m² land share · 1 parking space
50 homes · 19% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

South Tower 128 floors
South Tower 224 floors

South Tower 1: 139 homes, 87 m tall, 2 basements · South Tower 2: 118 homes, 78 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project37
Typical within 3 km (95)69
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project96%
Typical within 3 km (95)68%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.98 acres

28,227 m²

Ground covered by buildings
4% of the land

1,240 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
0.90 per home

232 covered, 0 open

Built-up area, all floors
3,36,544 sq ft

31,266 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 8 RERA projects of MANA PROJECTS PRIVATE LIMITED on the map

Complaints to RERA about its other projects

The company

Registered as
MANA PROJECTS PVT LTD
Type
Company
Company number
U45202KA2009PTC049111

CIN or LLPIN, from the Registrar of Companies.

PAN
AAFCM8997G
GSTIN
29AAFCM8997G1ZN
Website
MANAPROJECTS.COM

Its other registrations on RERA Karnataka

7 registrations under this company
  • MANA VERDANT TERRACES PRM/KA/RERA/1251/446/PR/041225/008303 · approved 4 Dec 2025
  • MANA VISTA PRM/KA/RERA/1251/308/PR/150325/007585 · approved 15 Mar 2025
  • MANA DALE PRM/KA/RERA/1251/446/PR/091123/006409 · approved 9 Nov 2023
  • MANA VERDANT PRM/KA/RERA/1251/309/PR/260523/005947 · approved 26 May 2023
  • MACASA EMERALD PRM/KA/RERA/1251/446/PR/101122/005450 · approved 10 Nov 2022
  • UBER VERDANT - II PRM/KA/RERA/1251/446/PR/190525/002575 · approved 25 May 2019
  • MANA TROPICALE PRM/KA/RERA/1251/446/PR/171015/000317 · approved 15 Oct 2017

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹24.0 crBuilding and development ₹246.0 crTotal ₹270.0 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹14.3 cr₹8.6 cr
Q4 2025-26₹27.0 cr₹19.1 cr
Q1 2026-27₹22.3 cr₹16.1 cr
Q2 2026-27₹34.6 cr₹22.7 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station5.81 kmReliable
  • Nearest railway station2.26 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km6Caveat
  • Nearest lake / water body (≥2 ha)0.68 kmCaveat

Hospitals

  • Nearest hospital1.69 kmCaveat

Schools

  • Schools in pincode 560035 (UDISE+ census)45Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)2Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBellanduru PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.42 kmReliable
  • Nearest sewage treatment plant3.3 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)7.56 kmCaveat
  • Nearest commercial-airport runway33.45 kmReliable
  • Distance to runway approach-path proxy32.92 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (12.88696, 77.70722), 2026-10-24. Each figure's source and caveat are in the full report.