Neighborhood IntelOpen on the map

RERA project · Mixed Development

Mahaveer Rarus

by REDDY STRUCTURES PRIVATE LIMITED · 20 homes · 0.62 acres · 2 towers · Bengaluru South

Past due, no completion filed Past its deadline of 30 Sep 2025, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 30 Sep 2025, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
32 homes per acre

Similar projects across the city: 79 per acre. 46% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 102 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?24 due so far
0% on time

Of its 27 RERA projects in Bengaluru Urban: 0 delivered on time, 8 late (after the date first promised), 16 past due with no completion filed, 3 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started19 Apr 2021
  2. Approved by RERA17 Aug 2022
  3. Deadline30 Sep 2025

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3BHK
1,249 sq ft
116 m² carpet · sizes 1,249–1,421 sq ft (4 at this size)
1 parking space
12 homes · 60% of the project
2.5BHK
1,152 sq ft
107 m² carpet
1 parking space
4 homes · 20% of the project
COMMERCIAL
7,673 sq ft
713 m² carpet · sizes 6,820–7,673 sq ft (3 at this size)
10 parking spaces
4 homes · 20% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Residential4 floors
Commercial4 floors

Residential: 16 homes, 1 basement · Commercial: 4 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project32
Typical in the city (114)79

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project46%
Typical in the city (118)63%

The share of the land not built on, which includes roads.

Land
0.62 acres

2,529 m²

Ground covered by buildings
54% of the land

1,374 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active mixed development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 27 RERA projects of Mahaveer Group on the map

Complaints to RERA about its other projects

102 complaints across 7 projects. The most complained about:

Show all 7 projects
  • Mahaveer Highlands 1 complaint
  • MAHAVEER WILLET 1 complaint

The company

Registered as
REDDY STRUCTURES PRIVATE LIMITED
Type
Company
Company number
U07010KA2002PTC031181

CIN or LLPIN, from the Registrar of Companies.

PAN
AACCR6953L

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹9.5 cr
Construction
₹15.8 cr
Total project cost
₹25.3 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.