by Legacy Global Projects Private Limited · 276 homes · 3.00 acres · 1 tower · Bengaluru North
Upcoming Under construction, due Dec 2028, after an extension. 47% built with 80% of the time used. 7% of homes booked.
At a glance
Due 31 Dec 2028. 80% of the time from RERA approval to the deadline has passed.
20 of 276 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 37 per acre. 61% of the land is left open.
Complaints to RERA about this project. 4 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 12 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 7 past due with no completion filed, 3 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started30 Jun 2016
- Approved by RERA15 Oct 2017
- First promised31 Jul 2020
The date the builder gave at registration.
- Today24 Oct 2026
80% of the time to the deadline has passed.
- Deadline (extended)31 Dec 2028
The date it must be complete by.
- If it slips like a typical project2 Oct 2029
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 28 × 1BHK, 156 × 2BHK, 72 × 3BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
Legacy Vivienda: 276 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Outdoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Gas
- Water and Sanitation
- Air Conditioning And incerntion
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.00 acres
- Ground covered by buildings
- 39% of the land
12,140 m²
4,685 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 12 RERA projects of Legacy Global Projects Private Limited on the map
Complaints to RERA about its other projects
- Legacy Salvador 2 complaints
- Legacy Eldora 1 complaint
- Legacy Cirocco 1 complaint
The company
- Registered as
- Legacy Global Projects Private Limited
- Type
- Company
- Company number
- U74140KA2008PTC044851
- PAN
- AABCL5654P
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/309/PR/171015/000885 · Approved
- Building plan approvedBIAPPA - Bangalore Airport Area Planning Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q2 2026-27 update
Complaints to RERA about this project
- Refusal to Honour Terms of Sale Agreement 29 May 2020 · Disposed Authority Bench5
- Refund of Sale Consideration with Interest and Compensation 24 Nov 2020 · Disposed Authority Bench5
- As per the complaint uploaded. 9 Mar 2021 · Disposed Authority Bench5
- As per the complaint uploaded. 9 Mar 2021 · Disposed Authority Bench5
- As mentioned in the complaint uploaded 9 Mar 2021 · Disposed Authority Bench5
- As per mentioned in the Complaint in the previous page. 20 Apr 2021 · Disposed Authority Fullbench
- As per the Complaint uploaded. 31 May 2021 · Disposed Authority Bench5
- As per the complaint. Breach of agreement. 8 Jul 2021 · Disposed Authority Fullbench
- Non completion of the Project 15 Dec 2021 · Disposed Authority Bench5
- Complaint under section 31(1) of the Real Estate (Regulation and Development) Rules, 2017 26 Dec 2022 · Disposed Authority Bench5
- Delay in competion and handing over of flat 9 May 2023 · Disposed Authority Bench5
- Withdrawal of Purchase of Property- Legacy Vivienda - A 105 5 Apr 2024 · Disposed Authority Bench4
- Complaint under section 31(1) of the Real Estate (Regulation and Development) Rules, 2017 6 Jan 2025 · Disposed Authority Bench4
- Complaint Under Section 31 (1) of the Real Estate (Regulation And Development) Act, 2016 Read With Rule 29 (1) of The Karnataka Real Estate (Regulation And Development) Rules, 2017 13 Feb 2025 · Disposed Authority Bench4
Documents
120 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹3.8 cr
- Construction
- ₹46.2 cr
- Total project cost
- ₹50.0 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹0.0 lakh | ₹0.0 lakh |
| Q4 2025-26 | ₹0.0 lakh | ₹0.0 lakh |
| Q1 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
| Q2 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station20.62 kmReliable
- Nearest railway station3.23 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km4Caveat
- Nearest lake / water body (≥2 ha)0.59 kmCaveat
Hospitals
- Nearest hospital4.21 kmCaveat
Schools
- Schools in pincode 562110 (UDISE+ census)3Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionChikkajala PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)3.59 kmReliable
- Nearest sewage treatment plant4.43 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)3.22 kmCaveat
- Nearest commercial-airport runway3.22 kmReliable
- Distance to runway approach-path proxy0 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (13.18569, 77.66062), 2026-10-24. Each figure's source and caveat are in the full report.