RERA project · Commercial
LEGACY MAXIMUS
by LEGACY GLOBAL PROJECTS PVT LTD · 12 homes · 0.79 acres · 1 tower · Bengaluru North
Upcoming Under construction, due Dec 2027. 55% built with 59% of the time used. 46% of homes booked.
At a glance
Due 31 Dec 2027. 59% of the time from RERA approval to the deadline has passed.
6 of 13 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 14 per acre. 64% of the land is left open.
Complaints to RERA about this project. 18 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 12 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 7 past due with no completion filed, 3 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started27 Jan 2022
- Approved by RERA31 Jan 2025
- Today24 Oct 2026
59% of the time to the deadline has passed.
- Deadline31 Dec 2027
The date it must be complete by.
- If it slips like a typical project1 Oct 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 7 × COMMERCIAL.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 10,436 sq ft8 homes969.5 m²
- 9,688 sq ft3 homes900.0 m²
- 8,584 sq ft1 home797.5 m²
- 9,978 sq ft1 home927.0 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Legacy Maimus: 13 homes, 64 m tall, 3 basements
Amenities
- Electricity 80 m²
- CCTV Surveillance 75 m²
- Power Backup 154 m²
- Water and Sanitation 246 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.79 acres
- Ground covered by buildings
- 36% of the land
- Floor-area ratio
- 4.25
- Parking
- 15.17 per home
- Built-up area, all floors
- 2,40,853 sq ft
3,211 m²
1,143 m²
Floors built per unit of land: 4.25 m² of floors for each m² of land.
182 covered, 0 open
22,376 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active commercial projects with a land area on RERA; the comparison is ours.
Who is building it?
All 12 RERA projects of Legacy Global Projects Private Limited on the map
Complaints to RERA about its other projects
- Legacy Vivienda 14 complaints
- Legacy Salvador 2 complaints
- Legacy Eldora 1 complaint
- Legacy Cirocco 1 complaint
The company
- Registered as
- LEGACY GLOBAL PROJECTS PVT LTD
- Type
- Company
- Company number
- U74140KA2008PTC044851
- PAN
- AABCL5654P
- GSTIN
- 29AABCL5654P1ZT
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
10 registrations under this company
- LEGACY MIHIRA PRM/KA/RERA/1250/303/PR/220725/007945 · approved 22 Jul 2025
- LEGACY MAXIMUS PRM/KA/RERA/1251/309/PR/181122/002150 · approved 22 Nov 2018
- LEGACY MYCON DUV PRM/KA/RERA/1251/309/PR/180420/001537 · approved 20 Apr 2018
- LEGACY CALISTA PRM/KA/RERA/1251/309/PR/180222/002428 · approved 22 Feb 2018
- Legacy Madelia PRM/KA/RERA/1251/309/PR/171024/000882 · approved 24 Oct 2017
- Legacy Cataleya PRM/KA/RERA/1251/309/PR/171016/000867 · approved 16 Oct 2017
- Legacy Cirocco PRM/KA/RERA/1251/309/PR/171016/000900 · approved 16 Oct 2017
- Legacy Eldora PRM/KA/RERA/1251/309/PR/171015/000833 · approved 15 Oct 2017
- Legacy Vivienda PRM/KA/RERA/1251/309/PR/171015/000885 · approved 15 Oct 2017
- Legacy Salvador PRM/KA/RERA/1251/309/PR/171015/000877 · approved 15 Oct 2017
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/309/PR/310125/007465 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · BBMP/ADDLDIR/JDCENTRAL/0017/19-20 · 11 May 2020
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBoreWell
Complaints to RERA about this project
None on RERA Karnataka.
Documents
183 files on the RERA page: Approved plan ↗, Commencement certificate ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹10.0 cr | ₹3.5 cr |
| Q4 2025-26 | ₹12.0 cr | ₹11.9 cr |
| Q1 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
| Q2 2026-27 | ₹11.1 cr | ₹7.8 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station0.42 kmReliable
- Nearest railway station2.63 kmReliable
- Bus stops within 500 m12Caveat
Parks, shops, daily needs
- Supermarkets within 1 km10Caveat
- Parks within 1 km5Caveat
- Nearest lake / water body (≥2 ha)1.83 kmCaveat
Hospitals
- Nearest hospital0.56 kmCaveat
Schools
- Schools in pincode 560025 (UDISE+ census)30Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km14Caveat
- Median pupil-teacher ratio, schools within 1 km22.4 :1Caveat
- Schools with library + playground + ICT lab (1 km)10Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionAshokanagara PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km2Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well30.3 m below groundCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km2Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)9.53 kmReliable
- Nearest sewage treatment plant1.38 kmCaveat
- Industrial zones within 1 km2Caveat
- Nearest airfield runway (any, incl. military)5.68 kmCaveat
- Nearest commercial-airport runway25.71 kmReliable
- Distance to runway approach-path proxy22.68 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.97173, 77.60729), 2026-10-24. Each figure's source and caveat are in the full report.