RERA project · Residential/Group Housing
LAPALAZZO RESIDENCES
by KRISHNA E CAMPUS PVT LTD · 96 homes · 1.89 acres · 4 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 6 Oct 2023, 1,832 days after the date it first promised.
At a glance
The builder filed for completion on 6 Oct 2023, 1,832 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started1 Oct 2013
- Approved by RERA14 Oct 2017
- First promised30 Sep 2018
The date the builder gave at registration.
- Completion filed6 Oct 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 3,180 sq ft15 homes295.4 m²
- 2,887 sq ft12 homes268.2 m²
- 2,993 sq ft11 homes278.1 m²
- 3,009 sq ft11 homes279.5 m²
- and 3 homes in other sizes
- 2,218 sq ft13 homes206.1 m²
- 2,232 sq ft12 homes207.4 m²
- 2,136 sq ft1 home198.4 m²
- 2,416 sq ft1 home224.5 m²
- and 1 home in other sizes
- 2,136 sq ft12 homes198.4 m²
- 2,993 sq ft2 homes278.1 m²
- 3,009 sq ft1 home279.5 m²
- 1,345 sq ft1 home125.0 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tarano: 28 homes, 2 basements · Cordona: 27 homes, 2 basements · Verona: 26 homes, 2 basements · Forano: 15 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
- Air Conditioning And incerntion
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
- Land
- 1.89 acres
- Ground covered by buildings
- 59% of the land
7,663 m²
4,558 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- KRISHNA E CAMPUS PVT LTD
- Type
- Company
- Company number
- U72200KA2001PTC028858
- PAN
- AACCK2999P
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171014/000301 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Delay of Possession/ Hand Over and Refund 21 Aug 2019 · Disposed Ao
- Refund the advance paid with interest 27 Aug 2019 · Disposed Ao
- Delayed Possession of Apartment 12 Dec 2019 · Disposed Authority Bench5
- Apartment not as advertised and not as specified 22 Jun 2022 · Disposed Authority Bench5
- Complaint directing Respondent to execute a registered agreement for sale in accordance with Section 13 of the Real Estate (Regulation and Development) Act, 2016 7 Dec 2022 · Disposed Authority Bench5
- Breach of Terms of Contract by way of failure to deliver possession on the due date 3 Apr 2023 · Disposed Authority Fullbench
- Compensation for Delay in handover 3 May 2023 · Disposed Authority Fullbench
- Delay of hand over of flat 16 Oct 2023 · Under Enquiry Authority Fullbench
- Delivery Date has expired and flat not handed over 17 Oct 2023 · Under Enquiry Authority Fullbench
- Flat not handed over despite payment 17 Oct 2023 · Under Enquiry Authority Fullbench
- Delay in delivery of flat 17 Oct 2023 · Under Enquiry Authority Fullbench
- Delay of hand over of flat 16 Oct 2024 · Under Enquiry Authority Fullbench
- Delay of hand over of flat 21 Oct 2024 · Under Enquiry Authority Fullbench
- Delay of hand over of flat 21 Oct 2024 · Under Enquiry Authority Fullbench
Documents
171 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹1.2 cr
- Construction
- ₹146.3 cr
- Total project cost
- ₹259.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.