Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

LAKESIDE 24

by SYLVAN ACRES REALTY PRIVATE LIMITED · 131 homes · 1.68 acres · 1 tower · Bengaluru East

Upcoming Under construction, due Oct 2028. 34% built with 58% of the time used. 91% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
34% built

Due 2 Oct 2028. 58% of the time from RERA approval to the deadline has passed.

Built34%
Time used58%
How much is sold?12 left
91% booked

119 of 131 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
78 homes per acre

Similar projects within 3 km: 70 per acre. 89% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?3 due so far
33% on time

Of its 4 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started3 Oct 2023
  2. Approved by RERA6 Mar 2024
  3. Today24 Oct 2026

    58% of the time to the deadline has passed.

  4. If it slips like a typical project4 Jul 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2620%
Q4 2025-2624%
Q1 2026-2728%
Q2 2026-2734%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

119 booked12 leftQ2 2026-27

Still available: 5 × 2 BHK, 1 × 2.5 BHK, 4 × 3 BHK, 2 × 4 BHK.

Booked, by type

2 BHK36 of 41
2.5 BHK40 of 41
3 BHK40 of 44
3.5 BHK1 of 1
4 BHK2 of 4

Booked, each quarter

Q3 2025-26101 of 131
Q4 2025-26118 of 131
Q1 2026-27120 of 131
Q2 2026-27119 of 131

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
940 sq ft
87 m² carpet · sizes 940–1,469 sq ft (21 at this size)
59 m² land share · 10 m² balcony/terrace · 1 parking space
44 homes · 34% of the project
2.5 BHK
848 sq ft
79 m² carpet · sizes 801–848 sq ft (21 at this size)
50 m² land share · 8 m² balcony/terrace · 1 parking space
41 homes · 31% of the project
2 BHK
763 sq ft
71 m² carpet
44 m² land share · 5 m² balcony/terrace · 1 parking space
41 homes · 31% of the project
4 BHK
1,422 sq ft
132 m² carpet · sizes 1,422–1,659 sq ft (1 at this size)
92 m² land share · 9 m² balcony/terrace · 1 parking space
4 homes · 3% of the project
3.5 BHK
1,131 sq ft
105 m² carpet
68 m² land share · 12 m² balcony/terrace · 1 parking space
1 home · 1% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Lakeside 2424 floors

Lakeside 24: 131 homes, 83 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project78
Typical within 3 km (65)70
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project89%
Typical within 3 km (66)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.68 acres

6,816 m²

Ground covered by buildings
11% of the land

724 m²

Floor-area ratio
2.01

Floors built per unit of land: 2.01 m² of floors for each m² of land.

Parking
1.22 per home

95 covered, 65 open

Built-up area, all floors
2,14,568 sq ft

19,934 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 4 RERA projects of Kolte-Patil on the map

The company

Registered as
SYLVAN ACRES REALTY PRIVATE LIMITED
Type
Company
Company number
U70102PN2005PTC021479

CIN or LLPIN, from the Registrar of Companies.

PAN
AAKCS3297G
GSTIN
29AAKCS3297G1ZT

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹11.7 crBuilding and development ₹78.6 crTotal ₹90.2 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹5.4 cr₹1.7 cr
Q4 2025-26₹5.9 cr₹1.8 cr
Q1 2026-27₹9.3 cr₹82.5 lakh
Q2 2026-27₹7.8 cr₹3.1 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station11.12 kmReliable
  • Nearest railway station6.15 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.58 kmCaveat

Hospitals

  • Nearest hospital0.12 kmCaveat

Schools

  • Schools in pincode 562149 (UDISE+ census)74Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBagalur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)0.75 kmReliable
  • Nearest sewage treatment plant4.52 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)5.44 kmCaveat
  • Nearest commercial-airport runway11.3 kmReliable
  • Distance to runway approach-path proxy9.24 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.09619, 77.64783), 2026-10-24. Each figure's source and caveat are in the full report.