RERA project · Plotted Development
Kumari Oak Ville
by Kumari Infra Homes · 4.37 acres · Anekal
Delivered late Completed: the builder filed for completion on 14 Mar 2025, 807 days after the date it first promised.
At a glance
The builder filed for completion on 14 Mar 2025, 807 days after the date it first promised.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started30 Jan 2019
- Approved by RERA13 Jan 2020
- First promised28 Dec 2022
The date the builder gave at registration.
- Completion filed14 Mar 2025
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 4.37 acres
- Plot area (the sites)
- 100% of the land
17,669 m²
17,669 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Kumari Infra Homes
- Type
- Partnership Firm
- PAN
- AAGCK0273Q
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/200113/003148 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Mental Harassment 13 Mar 2024 · Disposed Ao
- Mental Harassment 1 Apr 2024 · Disposed Ao
- Mental Harassment by builder 3 Apr 2024 · Disposed Ao
- Fradulent Sales of the villa plot to another party without any discloure to the registered user. 12 Jun 2024 · Disposed Authority Fullbench
- Delay in handingover of possession 19 Nov 2024 · Disposed Authority Fullbench
- Defective title of the property purchased by the Complainants 27 Nov 2024 · Disposed Authority Fullbench
- Defective title of the property purchased by the Complainant 28 Nov 2024 · Disposed Authority Fullbench
- Defective Title of the property purchased by the Compainants 2 Dec 2024 · Disposed Authority Fullbench
- Delay in handingover of possession 7 Jan 2025 · Disposed Authority Bench4
Documents
71 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹7.0 cr
- Construction
- ₹20.0 cr
- Total project cost
- ₹57.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station11.97 kmReliable
- Nearest railway station9.11 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km3Caveat
- Nearest lake / water body (≥2 ha)0.3 kmCaveat
Hospitals
- Nearest hospital2.57 kmCaveat
Schools
- Schools in pincode 562125 (UDISE+ census)91Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionSarjapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)14.98 kmReliable
- Nearest sewage treatment plant8.25 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)12.5 kmCaveat
- Nearest commercial-airport runway34.39 kmReliable
- Distance to runway approach-path proxy32.25 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (12.88378, 77.78627), 2026-10-24. Each figure's source and caveat are in the full report.