RERA project · Residential/Group Housing

KUMARAVANA

by ESSEM18 DEVELOPERS PRIVATE LIMITED · 91 homes · 1.47 acres · 1 tower · Bengaluru South

Upcoming Under construction, due Dec 2027. 58% built with 63% of the time used. 47% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
58% built

Due 31 Dec 2027. 63% of the time from RERA approval to the deadline has passed.

Built58%
Time used63%
How much is sold?48 left
47% booked

43 of 91 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
62 homes per acre

Similar projects within 3 km: 80 per acre. 54% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?3 due so far
33% on time

Of its 6 RERA projects in Bengaluru Urban: 1 delivered on time, 2 late (after the date first promised), 3 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started3 Apr 2024
  2. Approved by RERA31 Oct 2024
  3. Today24 Oct 2026

    63% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2647%
Q4 2025-2649%
Q1 2026-2751%
Q2 2026-2758%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

43 booked48 leftQ2 2026-27

Still available: 1 × 2 BHK, 1 × 2.5 BHK, 40 × 3 BHK, 6 × 4 BHK.

Booked, by type

2 BHK0 of 1
2.5 BHK0 of 1
3 BHK40 of 80
4 BHK3 of 9

Booked, each quarter

Q3 2025-2622 of 91
Q4 2025-2634 of 91
Q1 2026-2739 of 91
Q2 2026-2743 of 91

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,151 sq ft
107 m² carpet · sizes 1,005–1,198 sq ft (11 at this size)
66 m² land share · 20 m² balcony/terrace · 1 parking space
80 homes · 88% of the project
4 BHK
1,376 sq ft
128 m² carpet · sizes 1,151–1,376 sq ft (5 at this size)
67 m² land share · 28 m² balcony/terrace · 1 parking space
9 homes · 10% of the project
2 BHK
834 sq ft
78 m² carpet
47 m² land share · 12 m² balcony/terrace · 1 parking space
1 home · 1% of the project
2.5 BHK
1,025 sq ft
95 m² carpet
57 m² land share · 13 m² balcony/terrace · 1 parking space
1 home · 1% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower4 floors

Tower: 91 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project62
Typical within 3 km (64)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project54%
Typical within 3 km (66)50%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.47 acres

5,935 m²

Ground covered by buildings
46% of the land

2,746 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.21 per home

110 covered, 0 open

Built-up area, all floors
2,04,116 sq ft

18,963 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 6 RERA projects of Essem18 Developers Private Limited on the map

The company

Registered as
ESSEM18 DEVELOPERS PRIVATE LIMITED
Type
Company
Company number
U45205KA2016PTC085138

CIN or LLPIN, from the Registrar of Companies.

PAN
AAECE1601J
GSTIN
29AAECE1601J1ZU

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹31.5 crBuilding and development ₹88.2 crTotal ₹119.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹12.3 cr₹8.6 cr
Q4 2025-26₹20.1 cr₹13.2 cr
Q1 2026-27₹14.8 cr₹10.8 cr
Q2 2026-27₹12.4 cr₹8.7 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station2.13 kmReliable
  • Nearest railway station2.97 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km4Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)1.46 kmCaveat

Hospitals

  • Nearest hospital0.45 kmCaveat

Schools

  • Schools in pincode 560098 (UDISE+ census)29Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km2Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKengeri PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)11 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)12.68 kmReliable
  • Nearest sewage treatment plant2.06 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)16.31 kmCaveat
  • Nearest commercial-airport runway36.75 kmReliable
  • Distance to runway approach-path proxy31.84 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.90840, 77.50946), 2026-10-24. Each figure's source and caveat are in the full report.