KUMAR PLUMERIA

by KUMAR PROPERTIES PRIVATE LIMITED · 100 homes · 3.45 acres · 2 towers · Bengaluru North

Upcoming Under construction, due Dec 2028. 14% built with 45% of the time used. 5% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
14% built

Due 31 Dec 2028. 45% of the time from RERA approval to the deadline has passed.

Built14%
Time used45%
How much is sold?95 left
5% booked

5 of 100 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
29 homes per acre

Similar projects within 3 km: 95 per acre. 59% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
0% on time

Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 3 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started15 Jan 2025
  2. Approved by RERA21 Jan 2025
  3. Today24 Oct 2026

    45% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-268%
Q4 2025-2614%
Q1 2026-2714%
Q2 2026-2714%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block 114%
Block 20%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

5 booked95 leftQ2 2026-27

Still available: 36 × 3.5 BHK, 59 × NA.

Booked, by type

3.5 BHK4 of 40
NA1 of 60

Booked, each quarter

Q3 2025-264 of 100
Q4 2025-264 of 100
Q1 2026-275 of 100
Q2 2026-275 of 100

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

NA
1,762 sq ft
164 m² carpet · sizes 1,762–2,052 sq ft (30 at this size)
137 m² land share · 34 m² balcony/terrace · 2 parking spaces
60 homes · 60% of the project
3.5 BHK
1,693 sq ft
157 m² carpet · sizes 1,644–1,693 sq ft (30 at this size)
129 m² land share · 32 m² balcony/terrace · 2 parking spaces
40 homes · 40% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block 14 floors
Block 24 floors

Block 1: 50 homes, 15 m tall, 1 basement · Block 2: 50 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project29
Typical within 3 km (23)95
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project59%
Typical within 3 km (24)69%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.45 acres

13,961 m²

Ground covered by buildings
41% of the land

5,662 m²

Floor-area ratio
1.72

Floors built per unit of land: 1.72 m² of floors for each m² of land.

Parking
1.93 per home

185 covered, 8 open

Built-up area, all floors
3,74,519 sq ft

34,794 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 4 RERA projects of Kumar Properties on the map

Complaints to RERA about its other projects

The company

Registered as
KUMAR PROPERTIES PRIVATE LIMITED
Type
Company
Company number
U70101MH2000PTC216236

CIN or LLPIN, from the Registrar of Companies.

PAN
AABCK8464E
GSTIN
29AABCK8464E1ZB
Website
www.kumarworld.com

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹27.5 crBuilding and development ₹119.5 crTotal ₹146.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹5.0 lakh₹3.5 lakh
Q4 2025-26₹25.0 lakh₹17.5 lakh
Q1 2026-27₹53.2 lakh₹37.2 lakh
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station14.77 kmReliable
  • Nearest railway station7.8 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.81 kmCaveat

Hospitals

  • Nearest hospital1.96 kmCaveat

Schools

  • Schools in pincode 562149 (UDISE+ census)74Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBagalur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km32Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)2.71 kmReliable
  • Nearest sewage treatment plant6.19 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)4.59 kmCaveat
  • Nearest commercial-airport runway7.23 kmReliable
  • Distance to runway approach-path proxy5.43 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (13.13214, 77.65828), 2026-10-24. Each figure's source and caveat are in the full report.