RERA project · Plotted Development
KNS KALPA
by KNS Infrastructure Private Limited · 5.37 acres · Bengaluru South
Delivered late Completed: the builder filed for completion on 10 Aug 2022, 1,228 days after the date it first promised.
At a glance
The builder filed for completion on 10 Aug 2022, 1,228 days after the date it first promised.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 37 RERA projects in Bengaluru Urban: 7 delivered on time, 16 late (after the date first promised), 6 past due with no completion filed, 8 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started5 Aug 2017
- Approved by RERA21 Oct 2017
- Completion filed10 Aug 2022
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.37 acres
- Plot area (the sites)
- 55% of the land
21,751 m²
11,942 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 37 RERA projects of KNS Group on the map
The company
- Registered as
- KNS Infrastructure Private Limited
- Type
- Company
- Company number
- U45201KA2007PTC044230
- PAN
- AADCK2086J
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171021/001146 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
None on RERA Karnataka.
Documents
47 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹4.4 cr
- Construction
- ₹2.6 cr
- Total project cost
- ₹8.1 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station6.14 kmReliable
- Nearest railway station7.62 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)0.39 kmCaveat
Hospitals
- Nearest hospital2.4 kmCaveat
Schools
- Schools in pincode 560060 (UDISE+ census)105Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionTavarekere PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km1Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)22.2 kmReliable
- Nearest sewage treatment plant3.51 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)25.61 kmCaveat
- Nearest commercial-airport runway41.58 kmReliable
- Distance to runway approach-path proxy35.12 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (12.92826, 77.41430), 2026-10-24. Each figure's source and caveat are in the full report.