by Janaadhar India Private Limited · 360 homes · 2.85 acres · 5 towers · Anekal

Delivered late Completed: the builder filed for completion on 31 Oct 2018, 92 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 31 Oct 2018, 92 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
126 homes per acre

Similar projects within 3 km: 83 per acre. 78% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?3 due so far
0% on time

Of its 3 RERA projects in Bengaluru Urban: 0 delivered on time, 3 late (after the date first promised).

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started31 Jul 2013
  2. Approved by RERA14 Oct 2017
  3. Completion filed31 Oct 2018

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2BHK
  • 462 sq ft270 homes42.9 m²
  • 454 sq ft90 homes42.2 m²
Typically 30 m² land share · 11 m² balcony/terrace · 1 parking space
360 homes · 100% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder listed the areas in sq ft; m² figures are converted.

Towers

t109 floors
T128 floors
T148 floors
T12A8 floors
T118 floors

t10: 72 homes · T12: 72 homes · T14: 72 homes · T12A: 72 homes · T11: 72 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project126
Typical within 3 km (5)83
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project78%
Typical within 3 km (5)82%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.85 acres

11,533 m²

Ground covered by buildings
22% of the land

2,578 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 3 RERA projects of Janaadhar India Private Limited on the map

Complaints to RERA about its other projects

The company

Registered as
Janaadhar India Private Limited
Type
Company
Company number
U45201KA2007PTC044522

CIN or LLPIN, from the Registrar of Companies.

PAN
AABCJ9912C

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹4.1 cr
Construction
₹47.0 cr
Total project cost
₹51.1 cr

CaveatCost as certified by the builder's chartered accountant at registration.