Delivered on time Completed: the builder filed for completion on 5 Oct 2020, by the date it promised.
At a glance
The builder filed for completion on 5 Oct 2020, by the date it promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 50% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started20 Jun 2018
- Approved by RERA27 Mar 2019
- Completion filed5 Oct 2020
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
- First promised31 Dec 2020
The date the builder gave at registration.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 844 sq ft52 homes78.4 m²
- 816 sq ft12 homes75.8 m²
- 921 sq ft10 homes85.6 m²
- 801 sq ft9 homes74.4 m²
- and 60 homes in other sizes
- 1,157 sq ft5 homes107.5 m²
- 1,103 sq ft4 homes102.5 m²
- 1,136 sq ft4 homes105.5 m²
- 1,024 sq ft3 homes95.1 m²
- and 13 homes in other sizes
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder listed the areas in sq ft; m² figures are converted.
Towers
Block A: 52 homes, 1 basement · Block B: 48 homes, 1 basement · Block C: 48 homes, 1 basement · Block D: 24 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.82 acres
- Ground covered by buildings
- 225% of the land
7,346 m²
16,528 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- jai infra
- Type
- Partnership Firm
- PAN
- AANFJ9495M
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/190327/002495 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
None on RERA Karnataka.
Documents
47 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹13.6 cr
- Construction
- ₹26.0 cr
- Total project cost
- ₹39.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.