RERA project · Residential/Group Housing
Innovative Oak Garden Phase-2
by M/s.Innovative Developers · 80 homes · 1.20 acres · 1 tower · Bengaluru East
Past due, no completion filed Past its deadline of 30 Aug 2019, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Aug 2019, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 54% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started4 Apr 2017
- Approved by RERA26 Oct 2017
- Deadline30 Aug 2019
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 883 sq ft22 homes82.0 m²
- 880 sq ft10 homes81.8 m²
- 886 sq ft3 homes82.3 m²
- 929 sq ft3 homes86.3 m²
- and 9 homes in other sizes
- 741 sq ft6 homes68.8 m²
- 742 sq ft6 homes68.9 m²
- 732 sq ft3 homes68.0 m²
- 733 sq ft3 homes68.1 m²
- and 6 homes in other sizes
- 767 sq ft6 homes71.3 m²
- 763 sq ft1 home70.9 m²
- 764 sq ft1 home71.0 m²
- 883 sq ft1 home82.0 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Innovative Oak Garden Phase-2: 80 homes, 1 basement
Amenities
- Electricity
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.20 acres
- Ground covered by buildings
- 42% of the land
4,857 m²
2,041 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of M/s.Innovative Developers on the map
The company
- Registered as
- M/s.Innovative Developers
- Type
- Partnership Firm
- PAN
- AAEFI8062J
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171026/000855 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
None on RERA Karnataka.
Documents
40 files on the RERA page: Approved plan ↗, Commencement certificate ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹17.7 cr
- Construction
- ₹20.0 cr
- Total project cost
- ₹37.7 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.