RERA project · Residential/Group Housing
Iconica Nitesh Park Avenue
by Gardencity Realty Private Limited · 33 homes · 0.62 acres · 1 tower · Bengaluru North
Upcoming Under construction, due Jun 2028, after an extension. 56% built with 76% of the time used. 15% of homes booked.
At a glance
Due 30 Jun 2028. 76% of the time from RERA approval to the deadline has passed.
5 of 33 homes, as the builder reported for Q2 2026-27.
Similar projects across the city: 76 per acre. 89% of the land is left open.
Complaints to RERA about this project. 1 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 past due with no completion filed, 1 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started30 Sep 2013
- Approved by RERA28 May 2021
- First promised30 Dec 2021
The date the builder gave at registration.
- Today24 Oct 2026
76% of the time to the deadline has passed.
- Deadline (extended)30 Jun 2028
The date it must be complete by.
- If it slips like a typical project1 Apr 2029
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 1 × 2BHK, 5 × 3BHK, 22 × 4BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 3,629 sq ft20 homes337.1 m²
- 3,823 sq ft2 homes355.2 m²
- 1,767 sq ft5 homes164.2 m²
- 1,826 sq ft5 homes169.6 m²
- 903 sq ft1 home83.9 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
A: 33 homes, 3 basements
Amenities
- Electricity
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.62 acres
- Ground covered by buildings
- 11% of the land
2,508 m²
285 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of GARDENCITY REALTY PVT LTD on the map
Complaints to RERA about its other projects
- Iconica Nitesh Knightsbridge 1 complaint
The company
- Registered as
- Gardencity Realty Private Limited
- Type
- Company
- Company number
- U70200KA2004PTC033885
- PAN
- AACCG2140G
CIN or LLPIN, from the Registrar of Companies.
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERATOR/PRM/KA/RERA/1251/309/PR/210528/001913 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q2 2026-27 update
Complaints to RERA about this project
None on RERA Karnataka.
Documents
148 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹54.1 cr
- Construction
- ₹54.1 cr
- Total project cost
- ₹108.1 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q1 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
| Q2 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.