RERA project · Residential/Group Housing
HEART OF HARMONY
by CKPC RESIDENCES PRIVATE LIMITED · 137 homes · 1.83 acres · 1 tower · Bengaluru South
Upcoming Under construction, due Mar 2030. 6% built with 14% of the time used. 36% of homes booked.
At a glance
Due 1 Mar 2030. 14% of the time from RERA approval to the deadline has passed.
49 of 137 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 77 per acre. 85% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
None of its 2 RERA projects in Bengaluru Urban has reached its deadline yet.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Approved by RERA31 Mar 2026
- Work started1 Jun 2026
- Today24 Oct 2026
14% of the time to the deadline has passed.
- Deadline1 Mar 2030
The date it must be complete by.
- If it slips like a typical project1 Dec 2030
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 1 × 1 BED RESIDENCE, 7 × 3 BED CLASSIC-01, 9 × 3 BED CLASSIC-02, 6 × 3 BED CLASSIC-03, 13 × 3 BED CLASSIC-04, 4 × 3 BED PREMIUM- 01, 1 × 3 BED PREMIUM- 01A, 9 × 3 BED PREMIUM- 02, 1 × 3 BED PREMIUM- 02A, 3 × 3 BED PREMIUM- 03, 1 × 3 BED PREMIUM- 03A, 11 × 3 BED PREMIUM- 04, 1 × 3 BED STUDY LUXE - 1, 1 × 3 BED STUDY LUXE - 1A, 8 × 3 BED STUDY LUXE - 2, 1 × 3 BED STUDY LUXE - 2A, 1 × 4 BED GRAND- 01A, 1 × 4 BED GRAND-01, 9 × 4 BED GRAND-02.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower-1: 137 homes, 80 m tall, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House 1,087 m²
- Community Hall 146 m²
- Outdoor Sports facility 35 m²
- Indoor Sports facility 249 m²
- Swimming Pool 275 m²
- Gym 127 m²
- Power Backup 150 m²
- Water and Sanitation 337 m²
- Meet and Greet 100 m²
- Cycle Track 300 m²
- Jogging Track 300 m²
- Amphitheatre 96 m²
- Sculpture court 128 m²
- Tot Lot 66 m²
- Rock climbing 20 m²
- Multipurpose court 288 m²
- Pet Corner 23 m²
- Basket ball practice court 61 m²
- Outdoor Gym 35 m²
- Seating plaza 109 m²
- Nature trial 30 m²
- Reflexology path 17 m²
- Sky deck 175 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.83 acres
- Ground covered by buildings
- 15% of the land
- Floor-area ratio
- 3.24
- Parking
- 1.37 per home
- Built-up area, all floors
- 3,64,832 sq ft
7,411 m²
1,124 m²
Floors built per unit of land: 3.24 m² of floors for each m² of land.
188 covered, 0 open
33,894 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of CKPC RESIDENCES PRIVATE LIMITED on the map
The company
- Registered as
- CKPC RESIDENCES PRIVATE LIMITED
- Type
- Company
- Company number
- U41000KA2025PTC196977
- PAN
- AAMCC3568N
- GSTIN
- 29AAMCC3568N1ZU
- Website
- https://www.ckpcproperties.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Winds of Change by CKPC PRM/KA/RERA/1251/472/PR/210525/007765 · approved 21 May 2025
The land is owned together with others (a joint development), including Bangalore Cables Private Limited.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/310326/008560 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · GBA/BSCC/1962/25-26 · 31 Mar 2026
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBWSSB
Complaints to RERA about this project
None on RERA Karnataka.
Documents
117 files on the RERA page.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q4 2025-26 | ₹0.0 lakh | ₹0.0 lakh |
| Q1 2026-27 | ₹5.9 cr | ₹0.0 lakh |
| Q2 2026-27 | ₹17.2 cr | ₹7.5 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station0.32 kmReliable
- Nearest railway station7.49 kmReliable
- Bus stops within 500 m3Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km4Caveat
- Nearest lake / water body (≥2 ha)0.41 kmCaveat
Hospitals
- Nearest hospital0.18 kmCaveat
Schools
- Schools in pincode 560068 (UDISE+ census)144Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km16Caveat
- Median pupil-teacher ratio, schools within 1 km33.2 :1Caveat
- Schools with library + playground + ICT lab (1 km)13Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionBandepalya PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)18 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km4Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well1 m below groundCaveat
- In an IISc groundwater-critical ward (2025 outlook)yesCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km2Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)1.17 kmReliable
- Nearest sewage treatment plant0.98 kmCaveat
- Industrial zones within 1 km6Caveat
- Nearest airfield runway (any, incl. military)6.43 kmCaveat
- Nearest commercial-airport runway33.3 kmReliable
- Distance to runway approach-path proxy31.49 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.89274, 77.63837), 2026-10-24. Each figure's source and caveat are in the full report.