by Sri Sumeru Realty Private Limited · 152 homes · 2.12 acres · 2 towers · Bengaluru South

Upcoming Under construction, due Mar 2027. 100% built with 85% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
100% built

Due 31 Mar 2027. 85% of the time from RERA approval to the deadline has passed.

Built100%
Time used85%
How much is sold?0 left
100% booked

152 of 152 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
72 homes per acre

Similar projects within 3 km: 64 per acre. 70% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
50% on time

Of its 4 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 2 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Feb 2024
  2. Approved by RERA6 Apr 2024
  3. Today24 Oct 2026

    85% of the time to the deadline has passed.

  4. If it slips like a typical project31 Dec 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2695%
Q4 2025-26100%
Q1 2026-27100%
Q2 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block-1100%
Block-2100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

152 booked0 leftQ2 2026-27

Booked, by type

1 BHK52 of 52
2 BHK66 of 66
3 BHK18 of 18
4 BHK16 of 16

Booked, each quarter

Q3 2025-26151 of 152
Q4 2025-26152 of 152
Q1 2026-27152 of 152
Q2 2026-27152 of 152

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 BHK
841 sq ft
78 m² carpet · sizes 779–936 sq ft (16 at this size)
54 m² land share · 7 m² balcony/terrace · 1 parking space
66 homes · 43% of the project
1 BHK
517 sq ft
48 m² carpet · sizes 513–628 sq ft (17 at this size)
35 m² land share · 5 m² balcony/terrace · 1 parking space
52 homes · 34% of the project
3 BHK
1,140 sq ft
106 m² carpet · sizes 1,140–1,410 sq ft (8 at this size)
79 m² land share · 12 m² balcony/terrace · 1 parking space
18 homes · 12% of the project
4 BHK
1,534 sq ft
142 m² carpet · sizes 1,534–1,547 sq ft (8 at this size)
104 m² land share · 15 m² balcony/terrace · 1 parking space
16 homes · 11% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block-19 floors
Block-29 floors

Block-1: 72 homes, 30 m tall, 1 basement · Block-2: 80 homes, 30 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project72
Typical within 3 km (16)64
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project70%
Typical within 3 km (16)64%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.12 acres

8,561 m²

Ground covered by buildings
30% of the land

2,604 m²

Floor-area ratio
1.99

Floors built per unit of land: 1.99 m² of floors for each m² of land.

Parking
1.23 per home

171 covered, 16 open

Built-up area, all floors
2,69,937 sq ft

25,078 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 4 RERA projects of SRI SUMERU REALTY PRIVATE LIMITED on the map

The company

Registered as
Sri Sumeru Realty Private Limited
Type
Company
Company number
U07010KA2005PTC035470

CIN or LLPIN, from the Registrar of Companies.

PAN
AAICS7169R
GSTIN
29AAICS7169R1Z5

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹16.6 crBuilding and development ₹82.4 crTotal ₹99.0 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹6.8 cr₹4.8 cr
Q4 2025-26₹5.6 cr₹10.0 cr
Q1 2026-27₹72.4 lakh₹0.0 lakh
Q2 2026-27₹1.5 cr₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station5.8 kmReliable
  • Nearest railway station10.15 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)1.34 kmCaveat

Hospitals

  • Nearest hospital0.56 kmCaveat

Schools

  • Schools in pincode 560082 (UDISE+ census)71Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km1Caveat
  • Schools with library + playground + ICT lab (1 km)0Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKaggalipura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)9.24 kmReliable
  • Nearest sewage treatment plant8.25 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)21.87 kmCaveat
  • Nearest commercial-airport runway45.99 kmReliable
  • Distance to runway approach-path proxy41.74 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.81508, 77.50552), 2026-10-24. Each figure's source and caveat are in the full report.