RERA project · Plotted Development
HABITAT
by Powerhills Constructions private limited · 6.45 acres · Anekal
Past due, no completion filed Past its deadline of 31 Dec 2019, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2019, and no completion is filed.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started5 Mar 2017
- Approved by RERA2 Nov 2017
- First promised31 Dec 2018
The date the builder gave at registration.
- Deadline (extended)31 Dec 2019
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 6.45 acres
- Plot area (the sites)
- 55% of the land
26,101 m²
14,264 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Powerhills Constructions private limited
- Type
- Company
- Company number
- U70100KA2015PTC083219
- PAN
- AAICP3187A
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171102/001798 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Obtaining of RERA certificate with falsified documents 3 Feb 2021 · Disposed Authority Fullbench
Documents
75 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹4.3 cr
- Construction
- ₹2.3 cr
- Total project cost
- ₹9.3 cr
CaveatCost as certified by the builder's chartered accountant at registration.