by GRC INFRA PVT LTD · 48 homes · 0.43 acres · 1 tower · Anekal

Delivered on time Completed: the builder filed for completion on 2 Nov 2022, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 2 Nov 2022, by the date it promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
113 homes per acre

Similar projects within 3 km: 70 per acre. 70% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?2 due so far
50% on time

Of its 8 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 6 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started15 Nov 2019
  2. Approved by RERA19 Feb 2020
  3. Completion filed2 Nov 2022

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

  4. First promised15 Nov 2022

    The date the builder gave at registration.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

1BHK
420 sq ft
39 m² carpet · sizes 420–581 sq ft (24 at this size)
22 m² land share
48 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

C Bloock4 floors

C Bloock: 48 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project113
Typical within 3 km (121)70
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project70%
Typical within 3 km (121)66%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.43 acres

1,720 m²

Ground covered by buildings
203% of the land

3,500 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 8 RERA projects of GRC INFRA on the map

Complaints to RERA about its other projects

The company

Registered as
GRC INFRA PVT LTD
Type
Company
PAN
AADCG6210G

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹1.1 cr
Construction
₹9.4 cr
Total project cost
₹10.5 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.43 kmReliable
  • Nearest railway station3.65 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km8Caveat
  • Nearest lake / water body (≥2 ha)0.44 kmCaveat

Hospitals

  • Nearest hospital1.95 kmCaveat

Schools

  • Schools in pincode 560099 (UDISE+ census)88Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km7Caveat
  • Median pupil-teacher ratio, schools within 1 km34.6 :1Caveat
  • Schools with library + playground + ICT lab (1 km)5Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionparappana AgraharaReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km5Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)3.83 kmReliable
  • Nearest sewage treatment plant1.62 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)7.4 kmCaveat
  • Nearest commercial-airport runway33.79 kmReliable
  • Distance to runway approach-path proxy32.96 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.88408, 77.68195), 2026-10-24. Each figure's source and caveat are in the full report.