GRAND LA CASA
by TBC Homes Infra Corp · 196 plots · 10.05 acres · Anekal
Delivered late Completed: the builder filed for completion on 20 Aug 2022, 38 days after the date it first promised.
At a glance
The builder filed for completion on 20 Aug 2022, 38 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 16 per acre. 45% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 7 RERA projects in Bengaluru Urban: 1 delivered on time, 3 late (after the date first promised), 3 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started14 Jul 2020
- Approved by RERA1 Dec 2020
- Completion filed20 Aug 2022
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by.
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 10.05 acres
- Plot area (the sites)
- 5% of the land
40,670 m²
2,229 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 7 RERA projects of TBC Homes Infra Corp on the map
The company
- Registered as
- TBC Homes Infra Corp
- Type
- Partnership Firm
- PAN
- AAPFT6148M
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/201201/003732 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Violation of agreement, harrasment 24 May 2024 · Disposed Authority Fullbench
Documents
174 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹13.4 cr
- Construction
- ₹6.1 cr
- Total project cost
- ₹19.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.