Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

GR SITARA

by GR CONSTRUCTIONS · 250 homes · 3.02 acres · 11 towers · Anekal

Upcoming Under construction, due Dec 2026. 100% built with 96% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
100% built

Due 31 Dec 2026. 96% of the time from RERA approval to the deadline has passed.

Built100%
Time used96%
How much is sold?0 left
100% booked

250 of 250 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
83 homes per acre

Similar projects within 3 km: 72 per acre. 54% of the land is left open.

Any complaints?See the list
1 complaint

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
0% on time

Of its 3 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started20 Jan 2022
  2. Approved by RERA11 Apr 2022
  3. Today24 Oct 2026

    96% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-26100%
Q4 2025-26100%
Q1 2026-27100%
Q2 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block A100%
Block B100%
Block C100%
BLock D100%
Block E100%
Block F100%
Block G100%
Block H100%
Block I100%
Block J100%
Block K100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

250 booked0 leftQ2 2026-27

Booked, by type

3 BHK250 of 250

Booked, each quarter

Q3 2025-26246 of 250
Q4 2025-26246 of 250
Q1 2026-27249 of 250
Q2 2026-27250 of 250

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
924 sq ft
86 m² carpet · sizes 874–1,117 sq ft (50 at this size)
46 m² land share · 14 m² balcony/terrace · 1 parking space
250 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block A5 floors
Block B5 floors
Block C5 floors
BLock D5 floors
Block E5 floors
Block F5 floors
Block G5 floors
Block H5 floors
Block I5 floors
Block J5 floors
Block K5 floors

Block A: 40 homes, 15 m tall, 2 basements · Block B: 30 homes, 15 m tall, 2 basements · Block C: 20 homes, 15 m tall, 1 basement · BLock D: 20 homes, 15 m tall, 1 basement · Block E: 20 homes, 15 m tall, 1 basement · Block F: 20 homes, 15 m tall, 1 basement · Block G: 20 homes, 15 m tall, 2 basements · Block H: 20 homes, 15 m tall, 2 basements · Block I: 20 homes, 15 m tall, 2 basements · Block J: 20 homes, 15 m tall, 2 basements · Block K: 20 homes, 15 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project83
Typical within 3 km (96)72
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project54%
Typical within 3 km (96)64%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.02 acres

12,241 m²

Ground covered by buildings
46% of the land

5,596 m²

Floor-area ratio
2.24

Floors built per unit of land: 2.24 m² of floors for each m² of land.

Parking
1.14 per home

285 covered, 0 open

Built-up area, all floors
2,75,319 sq ft

25,578 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 3 RERA projects of GR CONSTRUCTIONS on the map

The company

Registered as
GR CONSTRUCTIONS
Type
Partnership Firm
PAN
AADFG6207A
GSTIN
29AADFG6207A1ZU
Website
www.grconstructions.co.in

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development), including G R Constructions.

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹14.6 crBuilding and development ₹122.6 crTotal ₹137.3 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹5.4 cr₹4.8 cr
Q4 2025-26₹5.4 cr₹4.8 cr
Q1 2026-27₹5.4 cr₹4.8 cr
Q2 2026-27₹5.4 cr₹4.8 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station2.72 kmReliable
  • Nearest railway station4.36 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)0.75 kmCaveat

Hospitals

  • Nearest hospital2.18 kmCaveat

Schools

  • Schools in pincode 560099 (UDISE+ census)88Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km9Caveat
  • Median pupil-teacher ratio, schools within 1 km30.8 :1Caveat
  • Schools with library + playground + ICT lab (1 km)6Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionparappana AgraharaReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km5Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)3.39 kmReliable
  • Nearest sewage treatment plant1 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)7.7 kmCaveat
  • Nearest commercial-airport runway34.17 kmReliable
  • Distance to runway approach-path proxy33.24 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.88087, 77.67607), 2026-10-24. Each figure's source and caveat are in the full report.