Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

GR GREEN LINE

by G R INFRA · 112 homes · 1.38 acres · 2 towers · Bengaluru South

Delivered late Completed: the builder filed for completion on 1 Apr 2022, 411 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 1 Apr 2022, 411 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
81 homes per acre

Similar projects across the city: 76 per acre. 50% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?2 due so far
50% on time

Of its 2 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised).

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started15 Feb 2019
  2. Approved by RERA22 Jul 2019
  3. First promised14 Feb 2021

    The date the builder gave at registration.

  4. Completion filed1 Apr 2022

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3BHK
975 sq ft
91 m² carpet · sizes 859–1,113 sq ft (22 at this size)
52 m² land share · 22 m² balcony/terrace · 1 parking space
73 homes · 65% of the project
2BHK
758 sq ft
70 m² carpet · sizes 725–844 sq ft (8 at this size)
44 m² land share · 18 m² balcony/terrace · 1 parking space
39 homes · 35% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block A3 floors
Block B3 floors

Block A: 56 homes, 1 basement · Block B: 56 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project81
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project50%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.38 acres

5,585 m²

Ground covered by buildings
50% of the land

2,792 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of G R INFRA on the map

The company

Registered as
G R INFRA
Type
Partnership Firm
PAN
AASFG7131Q

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹20.1 cr
Construction
₹32.0 cr
Total project cost
₹52.1 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.