Past due, no completion filed Past its deadline of 31 Aug 2023, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Aug 2023, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 16 per acre. 49% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Mar 2021
- Approved by RERA19 Mar 2021
- Deadline31 Aug 2023
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. The builder filed the carpet area of all homes of a type together, so sizes marked "on average" are that total divided by the number of homes.
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 8.92 acres
- Plot area (the sites)
- 51% of the land
36,118 m²
18,303 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Ms Gokul Developers
- Type
- Partnership Firm
- PAN
- AARFG7753K
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/210319/004036 · Approved
- Building plan approvedKIADB - Karnataka Industrial Areas Development Board
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
None on RERA Karnataka.
Documents
93 files on the RERA page: Approved plan ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹64.0 cr
- Construction
- ₹22.2 cr
- Total project cost
- ₹86.3 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?