RERA project · Residential/Group Housing

Godrej Vanantara

by GODREJ IRISMARK PRIVATE LIMITED · 2,008 homes · 36.13 acres · 16 towers · Bengaluru South

Upcoming Under construction, due May 2031. 1% built with 9% of the time used. 98% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
1% built

Due 31 May 2031. 9% of the time from RERA approval to the deadline has passed.

Built1%
Time used9%
How much is sold?44 left
98% booked

1,964 of 2,008 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
56 homes per acre

Similar projects within 3 km: 71 per acre. 93% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?12 due so far
33% on time

Of its 29 RERA projects in Bengaluru Urban: 4 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 17 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA13 May 2026
  2. Work started15 May 2026
  3. Today24 Oct 2026

    9% of the time to the deadline has passed.

  4. If it slips like a typical project1 Mar 2032

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q1 2026-271%
Q2 2026-271%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A1%
Tower B1%
Tower C2%
Tower D2%
Tower E2%
Tower F2%
Tower G2%
Tower H1%
Tower J1%
Tower K124%
Tower L1%
Tower M1%
Tower N1%
Tower P1%
Tower Q128%
Tower R122%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

1,964 booked44 leftQ2 2026-27

Still available: 1 × 2BHK-2Toilet, 29 × 3BHK-3Toilet, 10 × 3BHK-2Toilet, 4 × 4BHK-4Toilet+Servant Room-Servant Toilet.

Booked, by type

2BHK-2Toilet561 of 562
3BHK-3Toilet975 of 1,004
3BHK-2Toilet300 of 310
4BHK-4Toilet+Servant Room-Servant Toilet128 of 132

Booked, each quarter

Q1 2026-271,713 of 2,008
Q2 2026-271,964 of 2,008

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK-3Toilet
1,180 sq ft
110 m² carpet · sizes 1,180–1,393 sq ft (256 at this size)
62 m² land share · 15 m² balcony/terrace · 1 parking space
1,004 homes · 50% of the project
2BHK-2Toilet
833 sq ft
77 m² carpet · sizes 833–1,143 sq ft (300 at this size)
38 m² land share · 8 m² balcony/terrace · 1 parking space
562 homes · 28% of the project
3BHK-2Toilet
1,127 sq ft
105 m² carpet · sizes 1,121–1,139 sq ft (186 at this size)
52 m² land share · 14 m² balcony/terrace · 1 parking space
310 homes · 15% of the project
4BHK-4Toilet+Servant Room-Servant Toilet
1,997 sq ft
186 m² carpet
92 m² land share · 24 m² balcony/terrace · 1 parking space
132 homes · 7% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A30 floors
Tower B30 floors
Tower C30 floors
Tower D30 floors
Tower E30 floors
Tower F30 floors
Tower G30 floors
Tower H30 floors
Tower J30 floors
Tower K32 floors
Tower L32 floors
Tower M32 floors
Tower N32 floors
Tower P32 floors
Tower Q32 floors
Tower R32 floors

Tower A: 122 homes, 95 m tall, 3 basements · Tower B: 122 homes, 95 m tall, 3 basements · Tower C: 122 homes, 95 m tall, 3 basements · Tower D: 122 homes, 95 m tall, 3 basements · Tower E: 122 homes, 95 m tall, 3 basements · Tower F: 122 homes, 95 m tall, 3 basements · Tower G: 122 homes, 95 m tall, 3 basements · Tower H: 122 homes, 95 m tall, 3 basements · Tower J: 122 homes, 95 m tall, 3 basements · Tower K: 130 homes, 101 m tall, 3 basements · Tower L: 130 homes, 101 m tall, 3 basements · Tower M: 130 homes, 101 m tall, 3 basements · Tower N: 130 homes, 101 m tall, 3 basements · Tower P: 130 homes, 101 m tall, 3 basements · Tower Q: 130 homes, 101 m tall, 3 basements · Tower R: 130 homes, 101 m tall, 3 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project56
Typical within 3 km (26)71
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project93%
Typical within 3 km (27)54%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
36.13 acres

1,46,229 m²

Ground covered by buildings
7% of the land

9,989 m²

Floor-area ratio
2.00

Floors built per unit of land: 2.00 m² of floors for each m² of land.

Parking
1.17 per home

2,153 covered, 201 open

Built-up area, all floors
35,20,161 sq ft

3,27,034 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 29 RERA projects of Godrej Properties on the map

The company

Registered as
GODREJ IRISMARK PRIVATE LIMITED
Type
Company
Company number
U68100MH2026PTC468577

CIN or LLPIN, from the Registrar of Companies.

PAN
AAMCG8139M
GSTIN
29AAMCG8139M1ZR

The land is owned together with others (a joint development), including Godrej Irismark Pvt Ltd ( Formarly known as Godrej Irismark LLP).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹300.1 crBuilding and development ₹2173.1 crTotal ₹2626.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q1 2026-27₹300.4 cr₹0.0 lakh
Q2 2026-27₹293.6 cr₹54.8 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station6.55 kmReliable
  • Nearest railway station12.12 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.88 kmCaveat

Hospitals

  • Nearest hospital2.12 kmCaveat

Schools

  • Schools in pincode 560083 (UDISE+ census)111Caveat
  • Median pupil-teacher ratio, schools within 1 km22.3 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionHulimavu PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km3Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)1.93 kmReliable
  • Nearest sewage treatment plant1.97 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)13.49 kmCaveat
  • Nearest commercial-airport runway40.03 kmReliable
  • Distance to runway approach-path proxy37.48 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.83796, 77.60220), 2026-10-24. Each figure's source and caveat are in the full report.