RERA project · Residential/Group Housing
Godrej Reflections - Phase-1
by M/s. Wonder Projects Development Private Limited · 265 homes · 6.22 acres · 3 towers · Bengaluru East
Past due, no completion filed Past its deadline of 1 Jan 2025, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 1 Jan 2025, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 66 per acre. 79% of the land is left open.
Complaints to RERA about this project. 4 more about the builder's other projects.
The RERA page doesn't say.
Of its 29 RERA projects in Bengaluru Urban: 4 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 17 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Approved by RERA29 Mar 2018
- Work started2 Apr 2018
- First promised1 Apr 2023
The date the builder gave at registration.
- Deadline (extended)1 Jan 2025
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 1,002 sq ft40 homes93.1 m²
- 1,111 sq ft36 homes103.2 m²
- 1,127 sq ft35 homes104.7 m²
- 1,512 sq ft35 homes140.5 m²
- and 92 homes in other sizes
- 507 sq ft14 homes47.1 m²
- 507 sq ft13 homes47.1 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Block A: 98 homes, 2 basements · Block B: 70 homes, 2 basements · Block C: 97 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 6.22 acres
- Ground covered by buildings
- 21% of the land
25,191 m²
5,255 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 29 RERA projects of Godrej Properties on the map
Complaints to RERA about its other projects
- Godrej Lake Gardens 4 complaints
The company
- Registered as
- M/s. Wonder Projects Development Private Limited
- Type
- Company
- Company number
- U70102MH2015PTC265969
- PAN
- AABCW6662N
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/180329/002843 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Ongoing land dispute on in court and wrong Sale agreement statement 25 Jul 2019 · Disposed Authority
- Environmental Clearance quashed by NGT 14 Feb 2020 · Disposed Ao
- Illegal registration of the residential apartment project 23 Mar 2020 · Disposed Authority Fullbench
- Refund of paid amount due to breach or agreement 17 May 2020 · Disposed Ao
- REFUND OF ADVANCE AMOUNT 11 Aug 2021 · Disposed Authority Bench4
- Payment of Interest and Compensation due to False Warrantee provided in Agreement of Sale and Quashing of Environment Clearance by Hon'ble NGT 23 Jun 2022 · Disposed Authority Bench4
- Builder forcing to withdraw from project with limited interest 8 Jul 2024 · Disposed Authority Fullbench
- Builder forcing to withdraw from project with limited interest 20 Aug 2024 · Disposed Authority Fullbench
Documents
79 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹59.6 cr
- Construction
- ₹239.8 cr
- Total project cost
- ₹299.4 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station3.97 kmReliable
- Nearest railway station3.96 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km5Caveat
- Parks within 1 km11Caveat
- Nearest lake / water body (≥2 ha)0.56 kmCaveat
Hospitals
- Nearest hospital0.6 kmCaveat
Schools
- Schools in pincode 560102 (UDISE+ census)38Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)4Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionBellanduru PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)18 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)2.76 kmReliable
- Nearest sewage treatment plant1.34 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)4.41 kmCaveat
- Nearest commercial-airport runway30.98 kmReliable
- Distance to runway approach-path proxy29.94 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.91014, 77.66944), 2026-10-24. Each figure's source and caveat are in the full report.