RERA project · Residential/Group Housing

Godrej Park Retreat Phase 2

by Godrej Properties Limited · 563 homes · 4.88 acres · 6 towers · Bengaluru East

Upcoming Under construction, due Jun 2028. 95% built with 67% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
95% built

Due 1 Jun 2028. 67% of the time from RERA approval to the deadline has passed.

Built95%
Time used67%
How much is sold?1 left
100% booked

562 of 563 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
116 homes per acre

Similar projects within 3 km: 69 per acre. 76% of the land is left open.

Any complaints?See the list
1 complaint

Complaints to RERA about this project. 64 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?12 due so far
33% on time

Of its 29 RERA projects in Bengaluru Urban: 4 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 17 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jun 2023
  2. Approved by RERA13 Jul 2023
  3. Today24 Oct 2026

    67% of the time to the deadline has passed.

  4. If it slips like a typical project3 Mar 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2679%
Q4 2025-2689%
Q1 2026-2795%
Q2 2026-2795%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower J99%
Tower K99%
Tower L99%
Tower M100%
Tower N100%
Tower P100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

562 booked1 leftQ2 2026-27

Still available: 1 × 3 BHK.

Booked, by type

2 BHK326 of 326
3 BHK219 of 220
1 BHK17 of 17

Booked, each quarter

Q3 2025-26561 of 563
Q4 2025-26561 of 563
Q1 2026-27562 of 563
Q2 2026-27562 of 563

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 BHK
679 sq ft
63 m² carpet · sizes 679–820 sq ft (242 at this size)
29 m² land share · 9 m² balcony/terrace · 1 parking space
326 homes · 58% of the project
3 BHK
904 sq ft
84 m² carpet · sizes 845–914 sq ft (56 at this size)
37 m² land share · 9 m² balcony/terrace · 1 parking space
220 homes · 39% of the project
1 BHK
428 sq ft
40 m² carpet · sizes 428–591 sq ft (15 at this size)
17 m² land share · 4 m² balcony/terrace · 1 parking space
17 homes · 3% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower J27 floors
Tower K27 floors
Tower L27 floors
Tower M15 floors
Tower N15 floors
Tower P15 floors

Tower J: 161 homes, 84 m tall, 1 basement · Tower K: 107 homes, 84 m tall, 1 basement · Tower L: 107 homes, 84 m tall, 1 basement · Tower M: 63 homes, 48 m tall, 1 basement · Tower N: 63 homes, 48 m tall, 1 basement · Tower P: 62 homes, 48 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project116
Typical within 3 km (94)69
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project76%
Typical within 3 km (94)68%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.88 acres

19,730 m²

Ground covered by buildings
24% of the land

4,652 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.10 per home

563 covered, 57 open

Built-up area, all floors
8,39,283 sq ft

77,972 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 29 RERA projects of Godrej Properties on the map

Complaints to RERA about its other projects

64 complaints across 13 projects. The most complained about:

Show all 13 projects
  • GODREJ PARK RETREAT 2 complaints
  • Godrej Woodscapes Phase 2 2 complaints
  • GODREJ LAKESIDE ORCHARD 2 complaints
  • Godrej Splendour Phase II 2 complaints
  • Godrej Woodland Phase 2 1 complaint
  • GODREJ BUDIGERE CROSS / GODREJ BENGAL LAMPS 1 complaint
  • GODREJ TIARA 1 complaint
  • GODREJ WOODS 1 complaint

The company

Registered as
Godrej Properties Limited
Type
Company
PAN
AAACG3995M
GSTIN
29AAACG3995M1ZX
Website
www.godrejproperties.com

Its other registrations on RERA Karnataka

17 registrations under this company
  • GODREJ FLORENNE PHASE III PRM/KA/RERA/1250/304/PR/121026/009010 · approved 12 Oct 2026
  • GODREJ FLORENNE PHASE II PRM/KA/RERA/1250/304/PR/150926/008943 · approved 15 Sep 2026
  • GODREJ FLORENNE PRM/KA/RERA/1250/304/PR/150926/008942 · approved 15 Sep 2026
  • Boulevard at Godrej Woodscapes PRM/KA/RERA/1251/446/PR/190826/008878 · approved 19 Aug 2026
  • Godrej Regent Park PRM/KA/RERA/1251/308/PR/150726/008810 · approved 15 Jul 2026
  • GODREJ PARKSHIRE PRM/KA/RERA/1250/304/PR/090126/008393 · approved 9 Jan 2026
  • GODREJ WOODS PRM/KA/RERA/1251/472/PR/121125/008248 · approved 12 Nov 2025
  • GODREJ TIARA PRM/KA/RERA/1251/309/PR/110625/007817 · approved 11 Jun 2025
  • GODREJ LAKESIDE ORCHARD PRM/KA/RERA/1251/446/PR/300924/007105 · approved 30 Sep 2024
  • Godrej Woodscapes Phase 2 PRM/KA/RERA/1251/446/PR/170524/006888 · approved 17 May 2024
  • Godrej Woodscapes PRM/KA/RERA/1251/446/PR/170524/006882 · approved 17 May 2024
  • Godrej Splendour Phase II PRM/KA/RERA/1251/446/PR/120123/005611 · approved 12 Jan 2023
  • Godrej Woodland Phase 2 PRM/KA/RERA/1250/304/PR/020922/005201 · approved 2 Sep 2022
  • Godrej Splendour PRM/KA/RERA/1251/446/PR/160622/005000 · approved 16 Jun 2022
  • GODREJ PARK RETREAT PRM/KA/RERA/1251/446/PR/280222/004736 · approved 28 Feb 2022
  • Godrej Woodland PRM/KA/RERA/1250/304/PR/210208/003856 · approved 8 Feb 2021
  • Godrej Aqua PRM/KA/RERA/1251/309/PR/190102/002277 · approved 2 Jan 2019

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹60.1 crBuilding and development ₹279.2 crTotal ₹339.3 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹12.7 cr₹3.1 cr
Q4 2025-26₹13.8 cr₹13.6 cr
Q1 2026-27₹19.9 cr₹13.5 cr
Q2 2026-27₹10.4 cr₹11.5 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station6.05 kmReliable
  • Nearest railway station1.65 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km11Caveat
  • Nearest lake / water body (≥2 ha)0.39 kmCaveat

Hospitals

  • Nearest hospital1.23 kmCaveat

Schools

  • Schools in pincode 560035 (UDISE+ census)45Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBellanduru PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.18 kmReliable
  • Nearest sewage treatment plant3.06 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)6.92 kmCaveat
  • Nearest commercial-airport runway32.84 kmReliable
  • Distance to runway approach-path proxy32.34 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (12.89246, 77.70561), 2026-10-24. Each figure's source and caveat are in the full report.