Godrej Athena

by Godrej Projects Development Limited · 330 homes · 6.52 acres · 3 towers · Bengaluru East

Upcoming Under construction, due Jan 2028. 58% built with 76% of the time used. 80% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
58% built

Due 14 Jan 2028. 76% of the time from RERA approval to the deadline has passed.

Built58%
Time used76%
How much is sold?65 left
80% booked

265 of 330 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
51 homes per acre

Similar projects within 3 km: 63 per acre. 59% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?12 due so far
33% on time

Of its 29 RERA projects in Bengaluru Urban: 4 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 17 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA9 Jan 2023
  2. Work started15 Jan 2023
  3. Today24 Oct 2026

    76% of the time to the deadline has passed.

  4. If it slips like a typical project15 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2638%
Q4 2025-2650%
Q1 2026-2753%
Q2 2026-2758%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower 178%
Tower 273%
Tower 332%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

265 booked65 leftQ2 2026-27

Still available: 30 × 1 BHK, 32 × 2 BHK, 1 × 2.5 BHK, 2 × 3.5 BHK.

Booked, by type

1 BHK0 of 30
2 BHK26 of 58
2.5 BHK0 of 1
3 BHK71 of 71
3.5 BHK168 of 170

Booked, each quarter

Q3 2025-26258 of 330
Q4 2025-26268 of 330
Q1 2026-27265 of 330
Q2 2026-27265 of 330

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3.5 BHK
1,337 sq ft
124 m² carpet
80 m² land share · 15 m² balcony/terrace · 1 parking space
170 homes · 52% of the project
3 BHK
1,147 sq ft
107 m² carpet
66 m² land share · 9 m² balcony/terrace · 1 parking space
71 homes · 22% of the project
2 BHK
1,028 sq ft
96 m² carpet · sizes 889–1,147 sq ft (30 at this size)
60 m² land share · 10 m² balcony/terrace · 1 parking space
58 homes · 18% of the project
1 BHK
291 sq ft
27 m² carpet
18 m² land share · 5 m² balcony/terrace
30 homes · 9% of the project
2.5 BHK
1,147 sq ft
107 m² carpet
66 m² land share · 9 m² balcony/terrace · 1 parking space
1 home · 0% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 14 floors
Tower 24 floors
Tower 34 floors

Tower 1: 150 homes, 15 m tall, 1 basement · Tower 2: 40 homes, 15 m tall, 1 basement · Tower 3: 140 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project51
Typical within 3 km (14)63
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project59%
Typical within 3 km (14)47%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.52 acres

26,388 m²

Ground covered by buildings
36% of the land

9,560 m²

Floor-area ratio
45672.90

Floors built per unit of land: 45672.90 m² of floors for each m² of land.

Parking
1.06 per home

349 covered, 0 open

Built-up area, all floors
7,09,384 sq ft

65,904 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 29 RERA projects of Godrej Properties on the map

The company

Registered as
Godrej Projects Development Limited
Type
Company
Company number
U70102MH2010PLC210227

CIN or LLPIN, from the Registrar of Companies.

PAN
AAECG0366L
GSTIN
29AAECG0366L1ZC

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹123.0 crBuilding and development ₹312.1 crTotal ₹435.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹20.8 cr₹38.1 cr
Q4 2025-26₹44.3 cr₹74.4 cr
Q1 2026-27₹21.5 cr₹22.4 cr
Q2 2026-27₹16.8 cr₹29.6 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station2.95 kmReliable
  • Nearest railway station3.03 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km5Caveat
  • Parks within 1 km8Caveat
  • Nearest lake / water body (≥2 ha)1.07 kmCaveat

Hospitals

  • Nearest hospital0.36 kmCaveat

Schools

  • Schools in pincode 560017 (UDISE+ census)25Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km18Caveat
  • Median pupil-teacher ratio, schools within 1 km21.4 :1Caveat
  • Schools with library + playground + ICT lab (1 km)9Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionH.A.L. PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well17.8 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.3 kmReliable
  • Nearest sewage treatment plant0.41 kmCaveat
  • Industrial zones within 1 km5Caveat
  • Nearest airfield runway (any, incl. military)2.04 kmCaveat
  • Nearest commercial-airport runway24.57 kmReliable
  • Distance to runway approach-path proxy23.5 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.96853, 77.66737), 2026-10-24. Each figure's source and caveat are in the full report.