RERA project · Residential/Group Housing
Godrej Air
by Godrej Housing Projects LLP · 487 homes · 5.30 acres · 8 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 27 Jul 2023, 208 days after the date it first promised.
At a glance
The builder filed for completion on 27 Jul 2023, 208 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 10% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 29 RERA projects in Bengaluru Urban: 4 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 17 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started26 Jul 2017
- Approved by RERA19 Aug 2017
- First promised31 Dec 2022
The date the builder gave at registration.
- Completion filed27 Jul 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower A: 62 homes, 1 basement · Tower B: 62 homes · Tower C: 62 homes · Tower D: 60 homes · Tower E: 74 homes · Tower F: 60 homes · Tower G: 60 homes · Tower H: 47 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.30 acres
- Ground covered by buildings
- 378% of the land
21,448 m²
81,029 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 29 RERA projects of Godrej Properties on the map
The company
- Registered as
- Godrej Housing Projects LLP
- Type
- Company
- PAN
- AANFG9969R
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/170819/000006 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Incorrect demand, no tax invoice , structural change and threat of cancellation 25 Mar 2019 · Disposed Ao
- Comply the Order dated 06-08-2019 10 Feb 2021 · Disposed Ao
- Compensation of lapse of services/amenities and fixing unsafe building facilities (lifts 28 Jul 2022 · Disposed Ao
Documents
58 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹90.0 cr
- Construction
- ₹226.5 cr
- Total project cost
- ₹316.5 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.