RERA project · Residential/Group Housing
GM GLOBAL TECHIES TOWN TOWER- A
by M/s.Gulam Mustafa Enterprises Pvt Ltd · 1,406 homes · 8.28 acres · 1 tower · Anekal
Upcoming Under construction, due Nov 2026, after an extension.
At a glance
99% of the time has passed. No construction update is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 64% of the land is left open.
Complaints to RERA about this project. 157 more about the builder's other projects.
The RERA page doesn't say.
Of its 3 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed, 1 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started18 Feb 2017
- Approved by RERA28 Sep 2017
- First promised18 Feb 2022
The date the builder gave at registration.
- Today24 Oct 2026
99% of the time to the deadline has passed.
- Deadline (extended)18 Nov 2026
The date it must be complete by.
- If it slips like a typical project20 Aug 2027
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower A: 1,406 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 8.28 acres
- Ground covered by buildings
- 36% of the land
33,516 m²
11,926 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 3 RERA projects of M/s.Gulam Mustafa Enterprises Pvt Ltd on the map
Complaints to RERA about its other projects
- GM GLOBAL TECHIES TOWN TOWER C 109 complaints
- GM ELEGANCE TOWER-1 (E-12) 41 complaints
- GM GLOBAL TECHIES TOWN TOWER-B (TOWER-2) 4 complaints
- GM GLOBAL TECHIES TOWN TOWER C:::PRM/KA/RERA/1251/308/PR/170928/001289 3 complaints
The company
- Registered as
- M/s.Gulam Mustafa Enterprises Pvt Ltd
- Type
- Company
- Company number
- U70100KA1982PTC004720
- PAN
- AAACT6320P
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/170928/001304 · Approved
- Building plan approvedKIADB - Karnataka Industrial Areas Development Board
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Cheat / Fraud by GM Infinite - Bangalore 20 Oct 2019 · Disposed Authority Bench6
- Flat given to different customer without notice and taking booking installment with fake promises 21 Dec 2019 · Disposed Ao
- Booking Amount Refund of Rs. 1 Lakh. 9 Feb 2022 · Disposed Authority Bench5
- Delay compensation from the RERA registration expiry date 20 Dec 2022 · Disposed Authority Bench5
- Global Techies Town Tower A - Possession delay and no compensation from builder. 5 Jan 2023 · Disposed Authority Bench5
- Delay Compensation 6 Jan 2023 · Disposed Authority Bench5
- Delay in the handover/completion of the project 9 Jan 2023 · Disposed Authority Bench5
- Nearly 2 years delay in delivery from promised delivery date 10 Jan 2023 · Disposed Authority Bench5
- The Delivery date extended by one More year, excluded the 9 months extension by RERA 24 Jan 2023 · Disposed Authority Bench5
- Delay in allotment of flat, no delivery date given by builder and no compensation given 2 Feb 2023 · Disposed Authority Bench5
- Not refunding the advance booking amount 28 Apr 2023 · Disposed Authority Bench5
- Delay in Delivery of Flat A2318 6 May 2023 · Disposed Authority Bench5
- DELAY COMPENSATION 6 May 2023 · Disposed Authority Bench5
- Delay compensation 6 May 2023 · Disposed Authority Bench5
- Project Delivery Date Expiry and No compensation provided 20 May 2023 · Disposed Authority Bench5
- Refund of security deposit 2 Jun 2023 · Disposed Authority Bench5
- Delivery of flat with delay compensation 5 Jun 2023 · Disposed Authority Bench5
- Refund with compensation of paid amount against the flat 28 Jun 2023 · Disposed Authority Bench5
- The delivery of flat is delayed beyond expectation leads to uncertainty and financial loss 20 Jul 2023 · Disposed Authority Bench5
- Delay in delivery of flat as per committed date 9 Aug 2023 · Disposed Authority Bench5
- Compensation for the delay 19 Aug 2023 · Disposed Authority Bench5
- Delayed Possession and Denied to pay compensation 21 Aug 2023 · Disposed Authority Bench5
- Return of amount 1 Sep 2023 · Disposed Authority Bench5
- Not refunding booking amount even after cancellation 10 Oct 2023 · Disposed Authority Bench5
- Not getting refund 9 Dec 2023 · Disposed Authority Bench5
- Delay compensation from the RERA registration expiry date 5 Jan 2024 · Disposed Authority Bench5
- Refund of advance booking amount 5 Jan 2024 · Disposed Authority Bench5
- Delivery/ possession of the Flats to the Allottee 10 Jan 2024 · Disposed Authority Fullbench
- Persistent Delays and Lack of Clear Completion Roadmap for project - Request for Compensation 10 Jan 2024 · Disposed Authority Bench5
- Persistent Delays and Lack of Clear Completion Roadmap for project - Request for Compensation 17 Jan 2024 · Disposed Authority Bench5
- NOT RETURNING REFUNDABLE DEPOSIT 18 Jan 2024 · Disposed Authority Bench5
- paid 6.2 lacs for A2416 on 23rd Dec 2023. No calls have been responded after taking the money 18 Jan 2024 · Disposed Authority Bench5
- Nearly 2 years delay in delivery from promised delivery date,Refund with compensation of paid amount against the flat and settlement on home loan 29 Feb 2024 · Disposed Authority Bench5
- Interest on delay period 25 Mar 2024 · Disposed Authority Bench5
- Interest on delay period 27 Mar 2024 · Disposed Authority Bench5
- Interest on delay period 2 Apr 2024 · Disposed Authority Bench5
- Refund of booking amount on cancellation 17 Apr 2024 · Disposed Authority Bench5
- Interest compensation due to delay in project 29 Apr 2024 · Disposed Authority Bench5
- Refund Required 10 Jun 2024 · Disposed Authority Bench5
- refund of amount with interest 11 Jun 2024 · Disposed Authority Bench5
- Urgent Request for Intervention from RERA Authority Regarding Delayed Completion and Compensation for Flat Purchase 14 Jun 2024 · Disposed Authority Bench5
- interest on delay period 18 Jun 2024 · Disposed Authority Bench5
- Project delivery is delayed far beyond the committed deadlines 27 Jun 2024 · Disposed Authority Bench5
- DELAY IN COMPLETION OF THE PROJECT 2 Jul 2024 · Disposed Authority Bench5
- Delayed possession and no cooperation from the Builder 8 Jul 2024 · Disposed Authority Bench5
- RERA Approval Expired- Seeking refund of the advance amount of Rs 200000/-. 20 Aug 2024 · Disposed Authority Bench5
- Insolvency/Bankruptcy of Builder "Gulam Mustafa Enterprises Pvt Ltd" and thereafter retention of Buyers details/rights by RERA across project handover to other promoter/builder/party 10 Sep 2024 · Posted For Orders Authority Fullbench
- Delayed construction in progress 17 Sep 2024 · Disposed Authority Bench5
- Booking Amount Not Refunded 15 Oct 2024 · Disposed Authority Bench5
- Non adherence to delivery date and refund of amount 19 Oct 2024 · Disposed Authority Bench5
- Compensation for delay in construction and handover 13 Nov 2024 · Disposed Ao
- Delay in construction and intention to cheat 19 Nov 2024 · Disposed Authority Bench5
- Delay in construction and intention to cheat 19 Nov 2024 · Disposed Authority Bench5
- Return of full amount with interest 30 Nov 2024 · Disposed Authority Bench5
- Complaint under RERA for Refund of Booking Amount with interest - GM GLOBAL TECHIES TOWN TOWER- A 21 Jan 2025 · Disposed Authority Bench5
- Complaint for Delay in handover of the possession and for Refund 23 Jan 2025 · Under Enquiry Authority Bench5
- Flat not completed by Builder 27 Jan 2025 · Under Enquiry Authority Bench5
- Project/flat is incomplete and stands undelivered as of today, violation of sale agreement, refund of principle along interest 7 Mar 2025 · Disposed Authority Bench5
- Project is not delivered within the agreed date, its overdue more than 2 years. No response from the builder. 28 May 2025 · Disposed Authority Bench5
- Delayed Possession – Reliefs Sought – Direction from the Authority – Completion of Project – Execution of Sale Deed in Favour of the Complainant 17 Oct 2025 · Under Enquiry Authority Bench5
- Exit from the Project and Refund 20 Jan 2026 · Under Enquiry Authority Bench5
- Project delayed from the builder 15 Apr 2026 · Under Enquiry Authority Bench5
- Project stalled and delayed by more than 3 years 12 May 2026 · Under Enquiry Authority Bench5
- Complaint Against Builder for Delay in Project Handover – Request for Compensation 25 May 2026 · Under Enquiry Authority Bench5
- Possession is delayed. I seek compensation from builder. 6 Jul 2026 · Under Enquiry Authority Bench5
- Delayed Construction - No Information a no progress communicated or shared 14 Oct 2026 · Scrutiny Completed
Documents
63 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹329.6 cr
- Construction
- ₹413.8 cr
- Total project cost
- ₹743.4 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.