Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Geown OASIS

by Geown Casper Properties Pvt Ltd · 117 homes · 6.62 acres · 23 towers · Anekal

Delivered late Completed: the builder filed for completion on 27 Aug 2021, 270 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 27 Aug 2021, 270 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
18 homes per acre

Similar projects across the city: 76 per acre. 72% of the land is left open.

Any complaints?See the list
6 complaints

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?4 due so far
50% on time

Of its 5 RERA projects in Bengaluru Urban: 2 delivered on time, 1 late (after the date first promised), 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started26 Sep 2014
  2. Approved by RERA6 Apr 2018
  3. First promised30 Nov 2020

    The date the builder gave at registration.

  4. Completion filed27 Aug 2021

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3BHK
1,254 sq ft
116 m² carpet · sizes 1,254–1,294 sq ft (29 at this size)
1 parking space
60 homes · 51% of the project
4BHK
1,767 sq ft
164 m² carpet · sizes 1,568–2,188 sq ft (21 at this size)
1 parking space
57 homes · 49% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Building-12 floors
Building-22 floors
Building-32 floors
Building-42 floors
Building-52 floors
Building-62 floors
Building-72 floors
Building-82 floors
Building-92 floors
Building-102 floors
Building-112 floors
Building-122 floors
Building-132 floors
Building-142 floors
Building-152 floors
Building-162 floors
Building-172 floors
Building-182 floors
Building-192 floors
Building-202 floors
Building-212 floors
Building-222 floors
Building-232 floors

Building-1: 9 homes · Building-2: 9 homes · Building-3: 9 homes · Building-4: 9 homes · Building-5: 9 homes · Building-6: 9 homes · Building-7: 9 homes · Building-8: 8 homes · Building-9: 5 homes · Building-10: 3 homes · Building-11: 3 homes · Building-12: 3 homes · Building-13: 3 homes · Building-14: 3 homes · Building-15: 3 homes · Building-16: 3 homes · Building-17: 3 homes · Building-18: 4 homes · Building-19: 3 homes · Building-20: 4 homes · Building-21: 2 homes · Building-22: 2 homes · Building-23: 2 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project18
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project72%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.62 acres

26,810 m²

Ground covered by buildings
28% of the land

7,390 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 5 RERA projects of Geown Casper Properties Private Limited on the map

The company

Registered as
Geown Casper Properties Pvt Ltd
Type
Company
Company number
U70100KA2012PTC065567

CIN or LLPIN, from the Registrar of Companies.

PAN
AAECG8772C

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹18.3 cr
Construction
₹46.6 cr
Total project cost
₹64.9 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?