Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

GARUDADRI GARDENS

by SRI GARUDADRI CONSTRUCTIONS · 56 homes · 0.72 acres · 1 tower · Bengaluru South

Delivered on time Completed: the builder filed for completion on 10 Jun 2025, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 10 Jun 2025, by the date it promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
77 homes per acre

Similar projects within 3 km: 78 per acre. 53% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
50% on time

Of its 2 RERA projects in Bengaluru Urban: 1 delivered on time, 1 past due with no completion filed.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started1 Jul 2023
  2. Approved by RERA29 Dec 2023
  3. Completion filed10 Jun 2025

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3 BHK
702 sq ft
65 m² carpet · sizes 650–1,065 sq ft (4 at this size)
60 m² land share · 14 m² balcony/terrace · 1 parking space
28 homes · 50% of the project
2 BHK
778 sq ft
72 m² carpet · sizes 704–1,028 sq ft (6 at this size)
46 m² land share · 12 m² balcony/terrace · 1 parking space
28 homes · 50% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Garudadri Gardens4 floors

Garudadri Gardens: 56 homes, 14 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project77
Typical within 3 km (56)78
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project53%
Typical within 3 km (57)50%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.72 acres

2,932 m²

Ground covered by buildings
47% of the land

1,391 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
2.21 per home

56 covered, 6 open

Built-up area, all floors
77,855 sq ft

7,233 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of SRI GARUDADRI CONSTRUCTIONS on the map

The company

Registered as
SRI GARUDADRI CONSTRUCTIONS
Type
Partnership Firm
PAN
ADVFZ8650A
GSTIN
29ADVFS8650A1ZJ

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹10.5 crBuilding and development ₹19.9 crTotal ₹30.3 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.34 kmReliable
  • Nearest railway station1.85 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km2Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)0.38 kmCaveat

Hospitals

  • Nearest hospital0.42 kmCaveat

Schools

  • Schools in pincode 560060 (UDISE+ census)105Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
  • Median pupil-teacher ratio, schools within 1 km16.5 :1Caveat
  • Schools with library + playground + ICT lab (1 km)4Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKengeri PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)13.6 kmReliable
  • Nearest sewage treatment plant1.23 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)18.09 kmCaveat
  • Nearest commercial-airport runway38.08 kmReliable
  • Distance to runway approach-path proxy32.93 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.90404, 77.49375), 2026-10-24. Each figure's source and caveat are in the full report.