RERA project · Residential/Group Housing
FRONTIER HEIGHTS
by FRONTIER SHELTERS PVT LTD · 269 homes · 2.51 acres · 6 towers · Bengaluru East
Past due, no completion filed Past its deadline of 30 Nov 2020, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Nov 2020, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Mar 2017
- Approved by RERA14 Dec 2017
- First promised30 Nov 2019
The date the builder gave at registration.
- Deadline (extended)30 Nov 2020
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
tower - 1: 45 homes, 1 basement · tower - 2: 45 homes, 1 basement · tower - 3: 60 homes, 1 basement · tower - 4: 60 homes, 1 basement · tower - 5: 58 homes, 1 basement · club house: 1 home, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
- Land
- 2.51 acres
- Ground covered by buildings
- 100% of the land
10,163 m²
10,163 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of FRONTIER SHELTERS PVT LTD on the map
The company
- Registered as
- FRONTIER SHELTERS PVT LTD
- Type
- Company
- Company number
- U45203KA2012PTC062614
- PAN
- AABCF9123H
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171214/001250 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Builder cancelled allotment and not provding refund details 21 Nov 2019 · Disposed Ao
- Veracity in Payment Plan 4 Mar 2020 · Disposed Ao
- Compensation for delay in possession of flat 2102 5 Apr 2021 · Disposed Authority Bench4
- Refund of the booking amount as not recieved the required approval documents on time for verification on time 7 Apr 2021 · Disposed Authority Fullbench
- Need monetary compensation as due to delayed possession 10 Apr 2021 · Disposed Authority Fullbench
- Compensation due to delay in possession and speed up the construction pace 11 Apr 2021 · Disposed Authority Fullbench
- DELAY IN POSSESION / COMPENSATION FOR DELAY IN POSSESION 12 Apr 2021 · Disposed Authority Fullbench
- Compensation due to delay in the project 14 Apr 2021 · Disposed Authority Fullbench
- Delay in possession. 18 Jun 2021 · Disposed Authority Fullbench
- Compensation against the delay in handover from builder ** NOT REFUND/CANCELLATION** 21 Jun 2021 · Disposed Authority Fullbench
- Compensation for delay in project as per RERA rules 13 Aug 2021 · Disposed Authority Fullbench
- Compensation due to delay in possession and speed up the construction pace 24 Aug 2021 · Disposed Authority Fullbench
- BUILDER DELAYED POSSESSION FOR 1.5 YEARS AND NOT COMPENSATING 11 Sep 2021 · Disposed Authority Fullbench
- Only Delayed Compensation 12 Sep 2021 · Disposed Authority Fullbench
- INTERIM RELIEF REGARDING IMMEDIATE POSSESSION PLUS COMPENSATION IN RESPECT OF DELAY IN DELIVERY OF THE FLAT AND VIOLATION OF THE AGREEMENT. ALSO, AT THE TIME OF ENTERING TO THE AGREEMENT IN THE 19 Nov 2021 · Disposed Authority Fullbench
- Project Delayed for more that 1.5 Years, Builder not paying compensation 22 Nov 2021 · Disposed Authority Fullbench
- Seeking compensation for the delay in possession 23 Nov 2021 · Disposed Authority Fullbench
- Delay Compensation and interest. 24 Nov 2021 · Disposed Authority Fullbench
- Complain for compensation and delay in possession 24 Nov 2021 · Disposed Authority Fullbench
- Delay in possession of the flat 24 Nov 2021 · Disposed Authority Fullbench
- Project getting delayed. Need compensation to manage the financial and mental stress. No response from the Builder. 29 Nov 2021 · Disposed Authority Fullbench
- complaint against the builder delay in competion and deviating original plan 30 Nov 2021 · Disposed Authority Fullbench
- Project delayed 3 Dec 2021 · Disposed Authority Fullbench
- Breach of possession, handover of apartment and compensation as per agreement and No reply from Builder for the same 7 Dec 2021 · Disposed Authority Fullbench
- Breach of possession, handover of apartment and compensation as per agreement and No reply from Builder for the same 7 Dec 2021 · Disposed Authority Fullbench
- COMPLETION OF PROJECT AT THE EARLIEST, COMPENSATION FOR THE DELAY 15 Dec 2021 · Disposed Authority Fullbench
- Possession delayed by more than 8 months 23 Dec 2021 · Disposed Authority Fullbench
- As per agreement, builder had to deliver the flat by 31-03-2020 but he keeps on extending the date by giving next date everytime. 18 Jan 2022 · Disposed Authority Fullbench
- Delay in Handing over the project / 27 Jan 2022 · Disposed Authority Fullbench
- Delay in Project delivery 31 Jan 2022 · Disposed Authority Fullbench
- Delay in Flat Handover & No project update 6 Feb 2022 · Disposed Authority Fullbench
- Compensation against delay in Unit Handover 7 Feb 2022 · Disposed Authority Fullbench
- Compensation on delay in possession and speed up the construction pace 22 Feb 2022 · Disposed Authority Fullbench
- FRONTIER HEIGHTS PROMISED TO DELIVER IT BY MARCH 2019, BUT KEEP DELAYING 16 Mar 2022 · Disposed Authority Fullbench
- Delay in possession- FLAT NO 3143, 13TH , C Block 21 Mar 2022 · Posted For Orders Authority Fullbench
- Project is delayed for a long time and no progress 25 Mar 2022 · Disposed Authority Fullbench
- Long delay and slow progress 25 Mar 2022 · Disposed Authority Fullbench
- DELAY Inteerst and Compensation as per RERA Act and Rules 28 Mar 2022 · Disposed Authority Fullbench
- DELAY OF THE PROJECT COMPLETION/POSSESSION AND ZERO COMPENSATION PAID BY THE BUILDER 8 Apr 2022 · Disposed Authority Fullbench
- Delay on Delivery 4 May 2022 · Disposed Authority Fullbench
- Compensation for Delay in Possession 10 May 2022 · Disposed Authority Fullbench
- Delay in Possession 30 May 2022 · Disposed Authority Fullbench
- Delay in possession / Compensation for delays 19 Jul 2022 · Disposed Authority Bench4
- Builder has failed to delivery the flat as per the date mentioned in the sale agreement 25 Aug 2022 · Disposed Authority Bench4
- Refund of booking amount of Rs.6,21,000.00 along with the interest 6 Feb 2023 · Disposed Authority Fullbench
- Delay in Project delivery 4 May 2023 · Disposed Authority Fullbench
- Delay in handing over possession 22 May 2023 · Disposed Authority Fullbench
- Delay in Possession and compensation for delay 26 May 2023 · Disposed Authority Fullbench
- Delay in handover of the project for 2.5+ years and no compensation provided 25 Sep 2023 · Disposed Authority Fullbench
- Compensation and Possession 18 Nov 2023 · Posted For Orders Authority Fullbench
- Booking amount refund not received after cancellation 5 Jan 2024 · Disposed Authority Fullbench
- AS PER FORM ‘O’ OF KARNATAKA REAL ESTATE (REGULATION AND DEVELOPMENT) RULES, 2017 – MEMORANDUM OF COMPLAINT UNDER SECTION 31 R/W SECTION 71 OF THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 16 Feb 2024 · Disposed Authority Fullbench
- SECTION 31 OF RERA 5 Jun 2024 · Disposed Authority Fullbench
- Complaint under section 31 of RERA 6 Jun 2024 · Disposed Authority Fullbench
- Interest on delay period 12 Aug 2024 · Disposed Authority Fullbench
- Claim for Compensation Due to Delay in Possession of Residential Flat and expedite handover 19 Nov 2024 · Disposed Authority Fullbench
- Claim for Compensation Due to Delay in Possession of Residential Flat and expedite handover 17 Dec 2024 · Disposed Authority Fullbench
- Claim for interest on delay period 2 Jan 2025 · Disposed Authority Fullbench
- COMPLETION OF PROJECT AT THE EARLIEST AND PROVIDE COMPENSATION FOR THE DELAY 6 Jan 2025 · Disposed Authority Fullbench
- COMPLETION OF PROJECT AT THE EARLIEST AND PROVIDE INTEREST ON DELAY PERIOD. 6 Jan 2025 · Disposed Authority Fullbench
- FLAT NO. 3051, ON TH E 5TH FLOOR, FRONTIER HEIGHTS 1 Jul 2025 · Disposed Authority Fullbench
- NON COMPLETION AND REGISTRATION OF FLAT NO 3052 29 Jul 2025 · Disposed Authority Fullbench
- To provide compensation for the delay in handing over possession of the flat 4051 13 Feb 2026 · Disposed Authority Fullbench
- Need Justice and help to get my flat booked at builder project where I invested my all hard earned money invested in builder flat with interest and compensation 23 Feb 2026 · Disposed Authority Fullbench
- possession of apartment bearing No.1021 along with interest on delay period 3 Mar 2026 · Disposed Authority Fullbench
- possession of Apartment bearing No.3053 along with interest on the delay period 3 Mar 2026 · Disposed Authority Fullbench
- Want of Possession of flat No 3151 with interest on delay period 6 Mar 2026 · Disposed Authority Fullbench
- possession is not delivered as per the agreement 24 Mar 2026 · Disposed Authority Fullbench
Documents
147 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹9.0 cr
- Construction
- ₹110.0 cr
- Total project cost
- ₹119.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.